EDA 2530 Commissioning Procedure for Cable and Wireless Access
1/153 22-FGC 101 0239/2 Uen Rev J 2010-04-01
©
Ericsson AB 2010
Commercial in confidence
197 (200)
Section 5.5; Added extra steps m, n, & o, to reboot the equipment in order
to update the change to the OBM IP address.
G
29-06-2009 Seventh Issue Changes:-
Additional configuration details added for Child#2 & Child#3 (EDA2530)
variants, which are subtended from CP SFP3 & SFP4 respectively.
Sec 7; Added Child#2/Child#3 CVID values range to the DLE Planning
table.
Sec 7.1; “Configure SFP Modules” – Defined the Parent CP port SFP3 to
subtend a Child#2. Defined the Parent CP port SFP4 to subtend Child#3.
Sec 7.2.3; Added new sub-section to configure CP port 3 for subtending
Child#2.
Sec 7.2.4; Added new sub-section to configure CP port 4 for subtending
Child#3.
Sec 7.5; Restructure existing section into sub-sections 7.5.1 to 7.5.3.
Sec 7.5.4; Added new sub-section detailing how to “Create S-VLANs on
the Parent to Subtend Child#2”.
Sec 7.5.5; Added new sub-section detailing how to “Create S-VLANs on
the Parent to Subtend Child#3”.
Sec 7.6; “Configure The IBM Sub-Interface” – Added C-VLAN id table to
include Parent, Child#2, & Child#3 values.
Sec 7.7; “Assign the IBM IP Address” – Redefine the L2 Interface Name
field to include the CVID value options for Parent, Child#2, & Child#3.
Sec 7.10; “Configure PVC Bridge Management” – Two new sets of PVC
config files available & organised into folders. Folder names are “PVC
Config Parent”, “PVC Config Child#2”, & “PVC Config Child#3”.
Sec 7.10.3 Two additional C-VLAN tables added for Child#2 & Child#3.
Showing C-VLAN value ranges of Child#2: 1201-1840 & Child#3: 2201-
2840.
H
24-02-2010 Eighth Issue Changes:-
Sections 1, 2, 3, and 5 amended to include 32 x SHDSL Units.
Section 3.3 Tools and Test Equipment lists revised to include SHDSL
modem, test telephone and HDF connectors.
Section 7 New table added with POTS site specific information required.
Various changes for Child#1 to be an EDA2510 or an EDA2530.