![EHRLE HSC1140-INOX Gas Installation And Operating Instructions Manual Download Page 37](http://html1.mh-extra.com/html/ehrle/hsc1140-inox-gas/hsc1140-inox-gas_installation-and-operating-instructions-manual_2368758037.webp)
300631 • 1/2018 • H.S.
37 of 82
5 Commissioning
Installation and Operating Instructions
High Pressure Cleaner, Hot Water, Stationary
HSC1140-INOX Gas
5
Commissioning
WARNING
Initial commissioning after installation must be carried out
professionally.
The measures prior to initial commissioning may only be carried out by
trained and qualified personnel.
5.1
Activities prior to initial commissioning
Proceed as follows for all system types before initial commissioning:
Check the oil level on the dipstick of the high pressure pump and top
up to the „max.“ mark if necessary.
Specification for gas-fired systems:
Only the type of gas (natural gas, liquid gas) specified on the burner
nameplate may be used as fuel.
WARNING
Ensure that the exhaust pipes are properly installed.
Only operate the high pressure cleaner with a properly installed flue
pipe.
The sliding chimney nozzle must be pushed onto the flue pipe before
initial operation. Otherwise the life and limb of persons may be
endangered.
Check the sliding chimney nozzle before the initial start-up whether it is
pushed on, if necessary push on the exhaust pipe.
Only start up the system with the exhaust pipe installed.
During the initial commissioning and four weeks afterwards, carry
out an exhaust gas immission measurement and readjust the burner if
necessary (for setting values see section 5.3, Burner setting values for
gas-fired systems).