UPS Adira (6kVA, 6kVA XL, 10kVA,
10kVA XL 1-phase)
UPS Installation and Connection
Adira series
40
6.
UPS Installation and Connection
The system may only be installed and connected by trained authorized electri-
cians in accordance with respective safety rules and regulations!
All requirements listed in the technical specifications concerning ambient and
operating conditions must be met, to ensure proper operation of the UPS.
Please note the following during set-up / installation of the UPS:
Avoid extreme temperatures and humidity.
Ensure proper vertical set-up, as predefined.
Allow adequate space for ventilation of the device. Ensure a proper flow
channel.
Pay attention to the system layout. When installing the device in superordi-
nate systems (e.g. machine, switchboard), it has to be ensured, that the
UPS is operated within the specified temperature range. In case of a
heat build-up in the installation room, it must be removed through adequate
powered ventilation.
The device may only be mounted on castors and a solid, weight bearing
and horizontal surface.
6.1
Notes on the installation
The UPS must be installed in a well-ventilated environment, far away from wa-
ter, flammable gas and corrosive agents.
–
Ensure that the fans on the front and back side of the UPS are not ob-
structed by anything. There should be at least half a meter of free space on
all sides.
–
If the UPS is unpacked in an environment with very low temperatures,
there is a danger of condensation and water droplets may form. In this
case you have to wait for the UPS to fully dry, inside and out, before you
continue with the installation or commission the device, as there may oth-
erwise be a risk of electric shocks.