Commissioning
DE1/DC1 variable frequency drives
x
First of all complete all measures for commissioning the DE1/DC1
variable frequency drive as described in the respective manual.
x
Check the settings and installations for the connection to the
EtherNet/IP fieldbus system which are described in this manual.
NOTICE
: Make sure that there is no danger in starting the motor.
Disconnect the driven machine if there is a danger in an incorrect
operating state.
x
For communications, parameter P-12 (drive control) must be
set as follows in the DE1 variable frequency drive: P12 = 3.
In addition P-34 (PDP Address needs to be set to 1 and the
P-35 (baud Rate) should be at 4 (115.2 kbit/s).
x
For communications, parameter P-12 (drive control) must be set
as follows in the DC1 variable frequency drive: P12 = 3 or 4. In
addition P-36 (PDP Address needs to be set to 1 and the P-36
(baud Rate) should be at 4 (115.2 kbit/s). If using PDI Accel Time
for adjusting ramp time, P-12 should be set to 4.
For detailed information on how to configure parameters, please
refer to user manual.
EDS file
The properties of an EtherNet/IP card are described in the
corresponding EDS file. This file is required in order to be able to
integrate a DC1/DE1 variable frequency drive into an EtherNet/IP
network.
The EDS file, named “DX-NET-ETHERNET2-2“, can be found
on the Internet at: www.eaton.com/drives
A
OEM
A
DC1
or
DE1
A
Downloads
Engineering the module
The following instructions explain how to configure the
communication module with a DE1/DC1 variable frequency drive.
x
Then connect the device to the EtherNet/IP environment.
You will need the following components to do so:
•
Head-end controller
•
Computer (for programming and configuration purposes)
•
DE1/DC1 variable frequency drive with DX-NET-ETHERNET2-2
connection
Figure 8. Engineering the module
1
PC (with configuration tool)
2
Head controller (I/O controller)
3
Switch
4
EtherNet/IP cable
5
DE1/DC-1 variable frequency drives
6
Motor
x
Switch the device on (turn on the power supply!).
x
Now configure the project. (For information on a detailed
configuration, please consult the manual provided by the PLC’s
manufacturer.)
x
Check the LED indicators.
The head-end controller must recognize the device address and the
module must light up green. See “LED indicators” on
page 5
.
Enable
There must always be a “HIGH” signal at DI1 on the DE1 or the
DC1 Enhanced VFD.