8
HEXXAGONAL BEAM Construction
This manual for the
DX Engineering
HEXXAGONAL BEAM Mark 2
is written in sections for
the various assemblies
. Each section of assembly instructions is titled with the
HEXXAGONAL
BEAM Mark 2
kit name and model number for easy reference.
The typical build sequence is:
1. Assemble the patented HEXX HUB
2. Center Post assembly
3. 5-Band Stainless Steel/PTFE Rigid Feeder System
Installation
4. Install the Center Post Rope Hub
5. Installation of the optional
DXE-FCC050-H05-A
Feedline Current Choke
6. Spreader assembly
7. Wire Element installation
8. Installation on a Mast and Rotator
9. SWR Testing
An outdoor area of about a minimum 30 foot square is required for assembly of this antenna.
There are parts made from fiberglass in this kit. Take normal precautions when handling any
fiberglass material. There may be fiberglass dust, slivers or particles present when the fiberglass
parts were manufactured. The use of typical fiberglass handling safety gear (gloves, dust mask, eye
shield, clothing, etc.) when handling and working with fiberglass is recommended. Use a damp rag
to wipe the parts.
Do not
use compressed air to clean fiberglass parts. Measures can be taken to
reduce exposure after a person has come in contact with fiberglass. Eyes should be flushed with
water and any area of exposed skin should be washed with soap and warm water to remove fibers.
Clothing worn while working with fiberglass should be removed and washed separately from other
clothing. The washing machine should be rinsed thoroughly after the exposed clothing has been
washed. Check with your local or state safety and/or environmental agencies for more detailed
precautions.
The use of a three foot tripod and a three foot mast pipe makes construction of the antenna easier
(see
Figure 1
).
Figure 1 - Using a temporary tripod and mast for
assembly at ground level
Sufficient space is required for the installation of the antenna on your
mast or tower.
The finished antenna is approximately 22 feet in diameter.