Spin Welder User’s Manual
Section 7 – Operational Setup
Page 51
Page 50
Dukane Manual Part Number 403-547-03
Dukane Manual Part Number 403-547-03
the bottom stop adjustment. The maximum stroke
is 7” (178mm). This gives the lowest achievable
height above the platen of 2.19” (55.6mm). The
stroke range you set determines the space you have
to load and unload the parts.
Setup Checklist
1. Attach Tooling
Make sure the upper tool nest is securely fastened
to the tooling hub. Also attach the lower tooling
fixture at this time.
2. Disable System
Before applying power, push the red Emergency
OFF switch in. This prevents any electrical or
pneumatic energy from being applied to the spin
welder.
3. Base Interface Cable
The Base Interface cable should be connected be-
tween the base connector and the press connector as
shown in Figure 7–2 . These are identified as (4) and
(18) on the major components view Figure 2–3.
4. Connect AC Power
Make sure the AC switch enclosure is securely
closed. Plug in the AC power cord to a 240 VAC
60Hz 3-phase outlet. This safely grounds the spin
welder. Leave the AC power switch OFF.
5. Connect Compressed Air
Turn the front air pressure regulator
all the way
counterclockwise. Turn the rear panel counterbal-
ance regulator
all the way counterclockwise.
The compressed air can now be connected. The air
connection is shown in detail in both Figures 4–3
and 6–6. The compressed air supply should be clean
and dry. If your compressed air quality is marginal,
install a prefilter to avoid contaminating the internal
regulators, solenoids and air cylinder in the spin
Tooling
(Typical)
J35
J8
Base Inter
face Cable
100 psi Air
240 VAC 3Ø/60Hz
Optional
Pre–Filter
Air
Lockout
10
Figure 7–2
Location of Setup Checklist Items