6
1.- INSTALLATION
1.1.- Installation outline
See figure 1.
1.2.- Positioning
The machine must be firmly secured on the floor, which will support the weight
of the washer-extractor and the pressure transmitted while spinning.
After unpacking the washer-extractor, the pieces that secure the floating part and
the chassis, which are necessary for the transportation must be removed.
In order to do
this, the front and back panels should be removed to access the fastening elements. They
are easily seen as they are red.
It is advisable to secure the washer-extractor with the bolts provided with it. In
order to do so, plastic plugs must be inserted into the previously drilled holes (Fig. 2).
The washer-extractor must be correctly levelled leaving a space at the back to
facilitate its maintenance.
1.3.- Water connection
If only cold water is available, water connection is carried out as shown in fig 3.
If hot water is available, connection will be performed as shown in figure 4. If
decalcified water is also available, connection will be performed as shown in Figure 5.
Necessary dynamic pressure: 2
÷
4 kg/cm
2
.
1.4.- Vapour connection
If vapour is available, heating of washing water will be injected directly. The
connection diagram is shown in figure 6.
Vapour using pressure: 2
÷
4 kg/cm
2
.
After vapour has been introduced into the machine for the first time, it is
advisable for the vapour hose nuts to be re-tightened.
1.5.- Drainage
Fix the draining bend pipe as shown in figure 7.