Assembling towers in the upright
User Information
Load-bearing tower Staxo 40
Assembling in the upright with 'move-up' front and side railings
As a rule:
▪
Slide the diagonal cross onto the safety-catch bolt
and immediately secure it with the safety catch.
Installation example with Staxo 40 screw-jack foot
30cm and Staxo 40 4-way screw-jack head 30cm.
Erecting the first storey
➤
Insert screwjack base units.
➤
Link the frames with diagonal crosses.
Mounting the scaffold planking units
➤
Insert scaffold planking units.
➤
Close the anti-liftout guard.
Mounting the 'move-up' railings
➤
Mount the Staxo side railings.
Close-up of how to hang into place
NOTICE
▪
Erect the load-bearing tower in the vertical
on ground that is statically capable of sup-
porting the load.
▪
If the load-bearing tower is over 6
m high,
back-stay it or combine it with other towers.
F
Diagonal cross
98024-270-01
98024-314-01
98024-313-01
F
G
Scaffold planking 30/...cm
L
Staxo side railing
980 - -01
24 316
G
98024-295-01
980 - -01
24 315
L
L
98024-326-01