30
999805002 - 09/2018
System description
User Information
Load-bearing tower Staxo 40
Using bracket under concreting load
Extra shoring of bracket
The Staxo 40 bracket 90cm can also be used for trans-
ferring concreting loads. The extra plumbing strut
attached to every bracket ensures that no compressive
forces are transferred into the load-bearing tower.
Close-up showing how the plumbing strut is fixed
to the bracket
Close-up showing how the plumbing strut is fixed
to the ground
Anchoring the plumbing strut
The
Doka express anchor
can be re-used many times
over.
NOTICE
▪
Every frame with a bracket must be braced
by a Plumbing strut IB.
▪
The whole tower unit must be linked
together in a crane-handling-safe way using
Staxo 40 anti-dropout locks and Staxo 40
tube connectors.
See the section headed 'Lifting by crane'
98024-278-01
K
J
M
L
F
B
A
I
E
F
98024-297-01
A
L
K
N
O
P
A
Staxo
40 bracket 90cm
B
Staxo 40 screw-jack U-head or 4-way screw-jack head
E
Staxo 40 frame strut 1.40m
F
Plumbing strut 340 or 540 for precast members
J
Doka express anchor 16 Doka coil 16mm
K
Plumbing strut 340 IB or 540 IB
L
Staxo 40 plumbing strut adapter
M
Prop shoe
N
B25/90.5 pin
O
D16/122 pin
P
Linch pin 6x40 galv. DIN 11023
Q
d25/58 pin
R
Spring pin
Supporting force of the outermost screwjack on the
bracket:
Permissible Fmax: 10.5
kN
Reduction of 7.7 kN in the permitted vertical load F
V
per leg
Characteristic cube compressive strength of the con-
crete (f
ck,cube
):
min. 15
N/mm
2
(C12/15 grade concrete)
Follow Fitting Instructions!
Required safe working load of alternative anchors
for footplates:
R
d
≥ 20.3 kN (F
permissible
≥ 13.5 kN)
Follow the manufacturers' applicable fitting instruc-
tions.
98024-297-02
K
M
J
R
Q