Entry Pitch
Entry pitch is the slope of the drill frame compared with the slope of the ground. Determine entry pitch one
of two ways:
1.
With Pitch Beacon
•
Lay pitch beacon on the ground and read
pitch.
•
Lay pitch beacon on drill frame and read pitch.
•
Subtract ground pitch from drilling unit pitch.
2.
With Measurements
•
Measure from the ground to front end of drill
frame (H1).
•
Measure from the ground to back end of frame
(H2).
•
Subtract (H1) from (H2). Record this number.
•
Measure the distance between front and back
points (C).
•
Divide (H2-H1) by (C), then multiply by 100.
This is your pitch.
IMPORTANT:
A shallow entry pitch (A1) allows you
to reach horizontal sooner and with less bending.
Increasing entry pitch (A2) makes bore path longer
and deeper.
Summary of Contents for JT100
Page 1: ...JT100 JT100 All Terrain Tier 4 Issue 2 1 Original Instruction Operator s Manual 053 2814...
Page 105: ...Prepare 104 JT100 JT100 All Terrain Operator s Manual...
Page 247: ...Service 246 JT100 JT100 All Terrain Operator s Manual As Needed...
Page 255: ...Service Record 254 JT100 JT100 All Terrain Operator s Manual Service Performed Date Hours...
Page 258: ......
Page 259: ......