3.3
SETUP
Before setting up the ADCS-601-AF system, see Section 3.2 for information on site requirements.
ADCS-601-AF is a complex system made up of several sub-systems. Setting up and verifying the
complete system is an extensive, step by step, process in which the sequence of operations is
important. Always follow the instructions in Sections 3.3.1 to 3.4.6 in sequential order when setting
up and verifying the system. Allow a minimum of three hours to complete the process.
To set up the ADCS-601-AF system, first unpack it following the instructions in Section 3.1. Then follow
the set up instructions in Sections 3.3.1 to 3.3.13 sequentially. Once the system is set up, power it up,
initialize it and verify it following the instructions in Section 3.4.
Note all fittings, adaptors and parts mentioned in the setup instructions are included with the ADCS-601-AF
unless specifically stated otherwise. See the parts lists in Section 3.1 to locate all parts.
When assembling, use Teflon® tape or other appropriate thread sealer on all NPT thread fittings.
3.3.1
POSITION THE REFERENCE BENCH
Refer to the Site Requirements section of this manual and then position the bench and table
where you want them (See Section 3.2). Consider positioning of everything including gas
supplies, pumps, access to rear of system, DUT and computer.
Move the Control Cabinet out of the way until it is needed.