Steps
1.
Connect each server to the iSCSI network.
2.
Connect fault domain 1 (shown in orange) to the iSCSI network.
• Storage controller 1: port 1 to the Ethernet switch
• Storage controller 1: port 2 to the Ethernet switch
• Storage controller 2: port 1 to the Ethernet switch
• Storage controller 2: port 2 to the Ethernet switch
Example
Figure 55. Storage System in Virtual Port Mode with Dual 10 GbE Storage Controllers and One Ethernet
Switch
1.
Server 1
2.
Server 2
3.
Ethernet switch (Fault domain 1)
4.
Storage system
5.
Storage controller 1
6.
Storage controller 2
Next steps
Install or enable MPIO on the host servers.
NOTE: For the latest best practices, see the Dell Storage Center Best Practices document on the
Dell TechCenter site (
http://en.community.dell.com/techcenter/storage/
Connect the Front-End Cabling
69