5 Installation
Installation and operation manual
19
RYYQ+RYMQ+RXYQ8~20T7Y1B
VRV IV system air conditioner
4P370473-1C – 2016.07
Charging refrigerant
Step 6
Proceed with automatic or manual charge
Step 6b
Activate field setting [2-20]=1
Unit will start manual refrigerant charging operation.
Step 6a
• Push 1x BS2: "
888
"
• Push BS2 for more than 5 seconds "
t01
" pressure equalisation
• Open valve A
• Charge remaining amount of refrigerant P (kg)
R=Q+P
Depending on ambient conditions, the unit will decide to perform autocharge
operation in heating or cooling mode.
• Close valve A
• Push BS3 to stop manual charging
• Charging is finished
• Fill in the amount on the additional refrigerant charge label
• Input the additional refrigerant amount via setting [2-14]
• Go to test run
Step 5
• Connect valve A to the refrigerant charge port (d)
• Open all outdoor unit stop valves
R>Q
Automatic charge
Manual charge
Continued on next page >>
<< Continuation of previous page
p< p>
R410A
d
A