ESIE11-02
Piping Layout
1–63
3
1
4
5
Components water
side
The table below describes the main components of the refrigeration circuit on the water side.
No.
Component
Function / remark
a
Shut-off valve
Makes it possible to shut-off a part of the water
piping for maintenance (e.g. to change a filter).
b
Air purge
To purge the water circuit, to prevent air from
entering the water circuit.
c
Service port
The service port is used to connect a pressure
gauge.
d
Water tempera-
ture sensor
The water temperature sensors are used to control
the thermostat function at the heat exchanger inlet.
e
Freeze-up sensor
This protection device shuts down the circuit when
the temperature of the chilled water becomes too
low in order to prevent the water from freezing
during operation.
f
Strainer
This strainer prevents dirt particles from entering
the water circuit.
g
Flow switch
The flow switch is used to check if there is flow.
h
Drain valve
The drain valve is used to drain water from the
circuit.
i
Expansion vessel
The expansion vessel deals with water expansion,
which occurs when the temperature of the water
varies.
j
Pump
The pump circulates the water.
k
Pressure gauge
Standard is the pressure gauge fitted to the unit.
n
Safety valve
Maximum 3 bar pressure.
l
Buffer tank
This buffer tank of 55 l is used to store chilled water
to prevent the compressor from switching ON/OFF
continuously depending on the load.
m
Pressure regula-
tion valve
The pressure regulation valve is used to regulate
the pressure of the water side.
EUW
AB5-24KBZW1
EUW
AP5-24KBZW1
EUW
A
N5-24KB
Z
W1
Summary of Contents for EUWAB10KBZW1
Page 2: ......
Page 8: ...ESIE11 02 vi Table of Contents 3 1 4 5...
Page 10: ...Introduction ESIE11 02 viii 3 1 4 5...
Page 12: ...ESIE11 02 1 2 Part 1 System Outline 3 1 1 5...
Page 86: ...Wiring Layout ESIE11 02 1 76 Part 1 System Outline...
Page 88: ...ESIE11 02 2 2 Part 2 Functional Description 3 1 2 5...
Page 128: ...The Digital Controller ESIE11 02 2 42 Part 2 Functional Description 3 1 2 4 5...
Page 130: ...ESIE11 02 3 2 Part 3 Troubleshooting 3 1 3 5...
Page 168: ...ESIE11 02 4 2 Part 4 Commissioning and Test Run 3 1 4 5...
Page 198: ...Test Run and Operation Data ESIE11 02 4 32 Part 4 Commissioning and Test Run 3 1 4 5...
Page 200: ...ESIE11 02 5 2 Part 5 Maintenance 3 1 5...
Page 210: ...ESIE11 02 4 Index 3 1 4 5...