ESIE11-02
General Outline
1–21
3
1
4
5
(1)
: The table below contains the minimum water volume settings.
Oil charge volume
2.7 l
No. of circuits
1
Pump
No. x type
__
1 x Horizontal multi-stage end-suction
__
1 x Horizontal multi-stage end-suction
Model
__
CM5-3
__
CM5-3
Nominal static
height pump
__
237 kPa
__
223 kPa
Nominal static
height unit
__
167 kPa
__
123 kPa
Hydraulic components
Buffer tank
__
55 l
__
55 l
Unit water volume
3 l
3 l
59 l
3 l
3 l
59 l
Expansion vessel
__
12 l
__
12 l
Pre-pressure
expansion vessel
1.5 bar
1.5 bar
Safety valve
__
3 bar
__
3 bar
Dimensions
(h x w x d)
1450 x 1290 x 734 mm
Weight
Machine weight
258 kg
272 kg
284 kg
258 kg
272 kg
284 kg
Operation weight
261 kg
275 kg
343 kg
261 kg
275 kg
343 kg
Casing
Colour
Ivory white / Munsell code 5Y7.5/1 / ± RAL 7044
Material
Polyester coated galvanised steel plate
Sound power
level
(2)
78 dBA
Safety devices
■
Low-pressure switch
■
High-pressure switch
■
Pump motor overcurrent
■
Discharge temperature control
■
Outlet water temperature protection
■
Compressor motor overcurrent relay
■
Fan thermal protector
■
Anti-recycling and guard timer
■
Digital display controller with electronic temperature control
■
Reverse phase protector
■
Flow switch.
Model
EUWYN10KBZW1 EUWYP10KBZW1 EUWYB10KBZW1 EUWYN12KBZW1 EUWYP12KBZW1 EUWYB12KBZW1
Setting
EUWY*10-12KBZW1
The minimum water volume for standard thermostat difference setting
3 K
For reduced setting multiply this water volume by
3/new setting
Minimum allowable setting
0.1 K
Summary of Contents for EUWAB10KBZW1
Page 2: ......
Page 8: ...ESIE11 02 vi Table of Contents 3 1 4 5...
Page 10: ...Introduction ESIE11 02 viii 3 1 4 5...
Page 12: ...ESIE11 02 1 2 Part 1 System Outline 3 1 1 5...
Page 86: ...Wiring Layout ESIE11 02 1 76 Part 1 System Outline...
Page 88: ...ESIE11 02 2 2 Part 2 Functional Description 3 1 2 5...
Page 128: ...The Digital Controller ESIE11 02 2 42 Part 2 Functional Description 3 1 2 4 5...
Page 130: ...ESIE11 02 3 2 Part 3 Troubleshooting 3 1 3 5...
Page 168: ...ESIE11 02 4 2 Part 4 Commissioning and Test Run 3 1 4 5...
Page 198: ...Test Run and Operation Data ESIE11 02 4 32 Part 4 Commissioning and Test Run 3 1 4 5...
Page 200: ...ESIE11 02 5 2 Part 5 Maintenance 3 1 5...
Page 210: ...ESIE11 02 4 Index 3 1 4 5...