CAB INSTALLATION
9 of 30
4.6
Install self
-
adhesive seal around the edge of the
floorpan as shown and cut to length. Refer to
Figure 4.6a for
60”
and 4.6b for
72”.
Note: placement on the
72”
machine. Seal should
follow along the white line shown.
4.7
Insert spacer bushings into the depressions where
the floorboard bolts were removed.
(72”
uses 4
bushings,
60”
uses 6 bushings/spacers)
Hardware Used
Qty
1/2”
Long Spacer
4 or 6
4.8
Remove and discard the two screws securing the
voltage regulator to the frame.
4.9
Install the supplied secondary voltage regulator in
front of the OEM regulator with the following
hardware.
Hardware Used
Qty
M6x1.0x70mm Hex Head Bolt
2
M6x12 Steel Flat Washer
2
1.25”
Long Aluminum Spacer
2
Fig. 4.6a (Seal location on
60”)
Fig. 4.6b (Seal location on
72”)
Fig. 4.7 (Install Spacers)
Spacers
60”
Only
Fig. 4.9 (Install Secondary Regulator)
Secondary
Regulator