XI Start-up and Checkout
Use the following procedure for initial start-up of the boiler:
1) Make sure that the boiler is filled with water.
2) Check all new gas piping for leaks and purge piping sections that are filled with air. See the
National Fuel Gas
Code
for additional information on testing and purging gas lines.
3) Verify that vent system is complete and free of obstructions before attempting to fire boiler.
4) Inspect all wiring for loose or uninsulated connections.
5) Make sure the main burners are seated properly in the rear of burner tray and on orifices.
6) Adjust thermostat to the highest setting. Make sure the vent damper (if used) has fully opened.
7) Start the boiler using the appropriate lighting instructions for the gas valve on the boiler on page 34.
NOTE
SAFE LIGHTING AND OTHER PERFORMANCE CRITERIA WERE MET WITH THE GAS MANIFOLD
AND CONTROL ASSEMBLY PROVIDED ON THE BOILER WHEN THE BOILER UNDERWENT THE
TESTS SPECIFIED IN Z21.13.
WARNING
•
NEVER ATTEMPT TO FILL A HOT EMPTY BOILER
NOTE
The combustion chamber insulation panels in this boiler contain a cornstarch based binder which may emit a strong
odor as it is burned out of the insulation when the boiler is fired for the first time. An hour or more of continuous
firing may be required to burn off all of this binder. Open any windows and outside doors in the boiler room to
maximize ventilation while this binder is burned out.
Figure 23: Pilot Burner Flame
Figure 24: Main Burner Flame
Summary of Contents for 16 Series and
Page 2: ...2...
Page 4: ...4 2 II Specifications...
Page 12: ...12 10 Figure 6 Jacket Assembly...
Page 13: ...13 11 Figure 7 Gas Train Standard Build Figure 8 Gas Train CSD 1 Build 16 455 16 520 16 585...
Page 18: ...18 16 Figure 14 All Air From Outdoors Using Horizontal Ducts Into The Boiler Room...
Page 25: ...25 23 Figure 18 Standard Boiler Piping...
Page 26: ...26 Figure 19 Recommended Piping for Combination Heating Cooling Refrigeration System 24...
Page 30: ...30 28 Figure 21 Series 16 Standard Boiler Wiring...
Page 31: ...31 29 Figure 22 Series 16 CSD 1 Boiler Wiring...
Page 40: ...40 Figure 26 Exploded View Base Parts Manifold 38...
Page 42: ...42 Figure 27 Exploded View Base Heat Exchanger Flue Collector Assembly 40...
Page 44: ...44 42 Figure 28 Exploded View Jacket...
Page 46: ...46 44 Figure 29 Exploded View Trim Control Components...