Important: Should the machine fail to fill correctly or leak, turn off the shutoff valve and the
power to the machine before investigating the fault.
From the Engineers Menu, check the display on the front of the machine to ensure that the
water has heated to the correct temperature and that the machine is in standby mode.
All Models: Rotate soluble/freshbrew ingredient canister outlets to upright position. The
bean canister needs to have the outlet slide in the closed position before removal.
Note: For LINEA machines it is not necessary to remove the bean canister for it to be filled.
Remove the canister from the machine and remove
the lid. If a COTI machine, place canister into the
canister filling station inside the cabinet on the left
hand side and fill canister with correct ingredient. If
a LINEA machine, place canister on a clean, dry
surface.
DO NOT place the canister on the floor or overfill
with ingredient.
Carefully remove the canister from the filling station
and replace the lid. Refit canister into machine
ensuring that it is returned to the correct operating
station.
Repeat this operation for all soluble/freshbrew
ingredient canisters fitted to the machine. Rotate
the canister outlets to their correct operating
positions.
Note: After filling canisters, complete a bowl rinse.
Ensure that the agitator is removed for any freeze dried products and the canister blanking
bungs are clicked into position.
Bean Grinder Models: Close the outlet slide to seal the fresh beans canister outlet before
removing the canister from the machine. Remove the canister lid and hang the fresh beans
canister on the canister filling station. DO NOT place the canister on the floor.
Fill the canister with fresh coffee beans. Refit the canister lid and fit the canister into the
machine, ensuring that it is located correctly. Open the outlet slide to ensure correct
operation.
LINEA Espresso Model: Remove bean container lid using key, fill with fresh beans and
replace lid.
Note: To maintain optimum drink quality, Crane Merchandising Systems recommend that
the bean canister is replenished on a daily basis.
12
Summary of Contents for COTI
Page 1: ...Part No 403018 Issue April 2021 Technical Manual From software version 3 7 1 ...
Page 2: ......
Page 30: ...Section 3 Programming Mode 20 ...
Page 35: ...Section 4 Customising the User Interface Technical Manual 7 8 9 10 11 25 ...
Page 128: ...Section 8 Espresso System 8 2 1 Espresso Water Flow Diagram 118 ...
Page 148: ...Section 11 Electrical Electronic Diagrams Atlas H Board Pin Connections COTI 138 ...
Page 150: ...Section 11 Electrical Electronic Diagrams Atlas H Board Pin Connections LINEA 9 10 1 140 ...
Page 152: ...Section 11 Electrical Electronic Diagrams 11 8 Input Circuit 1 COTI 142 ...
Page 154: ...Section 11 Electrical Electronic Diagrams 11 10 Input Circuit 1 LINEA 144 ...
Page 156: ...Section 11 Electrical Electronic Diagrams 11 12 Output Circuit 1 COTI 146 ...
Page 158: ...Section 11 Electrical Electronic Diagrams 11 14 Output Circuit 1 LINEA 148 ...
Page 168: ...NOTES 158 ...
Page 169: ......