An Introduction to Dielectric Withstand Testing with the HT-10KVDC 

 

The dielectric withstand test is a test which is recognized by safety agencies worldwide as a valid 
criterion  of  safe  assembly  of  end-use  equipment.    The  HT-10KVDC  is  designed  as  a  research 
instrument to determine the dielectric properties of component assemblies of end-use equipment.  
It  applies  a  high-voltage  potential  between  Output  and  Return  test  leads  and  monitors  Leakage 
Current  and  watches  for  Dielectric  Breakdown  during  the  test.    To  aid  in  testing,  the  HT-
10KVDC can be configured with or without voltage ramp time, with or without a test duration 
timer,  and  can  be  set  to  deliver  high  voltage  after  an  arc  has  been  detected  to  allow  safety 
engineers to pinpoint the problem. 
 

The dielectric withstand test involves high voltage and caution should be exercised when 

using the HT-10KVDC.  The Return Jack on the front panel is connected to ground potential, and 
setups  should  be  designed  with  this  in  mind,  to  guard  against  the  operator  contacting  high 
voltage.  Always make sure the return lead is firmly connected.   

 

Leakage Test 

 
The HT-10KVDC leakage test uses a separate low-frequency circuit to detect excessive current 
as a result of low impedance between the Output and Return jacks on the front panel.  There is 
not  a  specific  leakage  current  level  pass/fail  requirement  at  this  time  for  most  equipment.  
However, higher than normal leakage current on a particular sample may indicate an assembly or 
component problem in the circuit.   
 

The  leakage  current  is  also  monitored  by  the  HT-10KVDC  to  ensure  that  excessive 

leakage does not keep the tester from developing full voltage required for the high voltage test.  
The  HT-10KVDC  will  provide  full  voltage  at  any  leakage  current  level  up  to  5  mA  DC.    The 
leakage current trip level is adjustable on the rear panel.   
 

If  the  green  Full  Voltage  LED  lights  and  the  test  continues,  the  leakage  current  was 

below the amount set by the rear panel adjustment. 
 

If the red Excess Leakage LED lights, the buzzer sounds, and the test is terminated, the 

leakage current was over the amount set by the rear panel adjustment.

   

 

High Voltage Dielectric Withstand Test 

 
 

This  test  checks  for  insulation  system  breakdowns  by  applying  a  high  voltage  between 

the  Output  and  Return  jacks  on  the  front  panel.    The  HT-10KVDC  uses  a  separate  high-
frequency circuit to detect arc breakdowns of greater than 100 nsec duration. 
 

The duration of the test is controlled by the test time control on the back panel.  The test 

time is counted from the time the Full Voltage LED is lit to the completion of the test.  The timer 
may be defeated, allowing the test to continue for as long as the TEST Button is pressed.  The 
minimum test time when the timer is defeated is one second. 
 

If  the  green  Hipot  Pass  LED  lights,  the  test  cycle  has  been  successfully  completed, 

meaning there was no dielectric breakdown, 
   

If the red Hipot Fail LED lights, a breakdown arc has been detected.

   

 

Summary of Contents for HT-10KVDC

Page 1: ...HT 10KVDC Dielectric Withstand Tester 0 14000 Volts DC Output Instruction Manual COMPLIANCE WESTUSA...

Page 2: ......

Page 3: ...panel and represents the latest in high voltage laboratory testing To fully appreciate all the features of your new meter we suggest that you take a few moments to review this manual Compliance West...

Page 4: ......

Page 5: ...justment of the Leakage Current Level 14 Adjustment of the High Voltage Ramp Time 15 Adjustment of the High Voltage Level 15 Adjustment of the High Voltage Test Duration 15 Setting the Voltage Ramp Sw...

Page 6: ......

Page 7: ...e supplied cordset Turn it on using the switch on the rear panel 2 Switch the Test Duration switch on the rear panel to the DEFEAT position 3 Push the RESET Button then push and hold the TEST Button T...

Page 8: ...ost equipment However higher than normal leakage current on a particular sample may indicate an assembly or component problem in the circuit The leakage current is also monitored by the HT 10KVDC to e...

Page 9: ...d test The HT 10KVDC should remain connected to the circuit until the green Hipot Pass light or the red Hipot Fail light on the front panel is lit and the output voltage as indicated on the front pane...

Page 10: ...cuit returns output voltage to safe levels before test termination The Hipot Pass or Hipot Fail light will not light until voltage has been ramped down by the HT 10KVDC If a failure is encountered the...

Page 11: ...p ON DEFEAT Timer Duration ON DEFEAT Failure Shutdown ON DEFEAT ENVIRONMENTAL Operating Temperature 15 40 C Relative Humidity Range 0 90 non condensing GENERAL Input power requirements Model HT 10KVDC...

Page 12: ...iginal shipping container for subsequent shipping If the original shipping container is not available be sure that adequate protection is provided to prevent damage during shipment Remove the Tester f...

Page 13: ...and Rear Panel Features The front panel features of the HT 10KVDC are shown in Figure 3 1 and described in Table 3 1 The rear panel features of the HT 10KVDC are shown in Figure 3 2 and described in T...

Page 14: ...9 Figure 3 1 Controls Indicators Connectors HT 10KVDC Front Panel...

Page 15: ...l light and if not defeated the high voltage duration time starts when the voltage output reaches the preset level 5 Hipot Fail LED Indicates failure of high voltage test If arcing or a flashover of t...

Page 16: ...11 Figure 3 2 Controls Indicators Connectors HT 10KVDC Rear Panel...

Page 17: ...e test duration See Adjustment of the High Voltage Test Duration section 16 Leakage Limit Adjustment Adjusts the alarm level for the excessive leakage current test See Adjustment of the Leakage Curren...

Page 18: ...mps should be lit 10 Disconnect the black lead from the red lead and remove both leads from the HT 10KVDC 11 Enable the voltage output by pressing the RESET button then the TEST button After the full...

Page 19: ...st the Leakage Limit control item 16 on the rear panel to its maximum clockwise position 4 Make sure there are no test leads connected to the Tester 5 Push the RESET button item 1 The blue TEST light...

Page 20: ...n the Test Timer switch item 12 to the DEFEAT position The HT 10KVDC will supply voltage while the TEST button item 2 is held in 2 Make sure there are no test leads connected to the HT 10KVDC 3 Press...

Page 21: ...testing after a failure is encountered This allows the operator to find a breakdown point but all safety shutdown circuitry in the HT 10KVDC is disabled when the Failure Shutdown switch is in the DEFE...

Page 22: ...t of the circuit under test is too high the Excess Leakage LED item 3 will light and the test will terminate If the Failure Shutdown Switch is set to DEFEAT and the requirements of Table 3 3 are met t...

Page 23: ...er test result means the equipment being tested failed a test phase If unanticipated test failures continue and you suspect that the equipment under test is built correctly check the following item 1...

Page 24: ...19 Voltage Ramp ON DEFEAT ON DEFEAT DEFEAT Test Timer ON ON DEFEAT DEFEAT DEFEAT Failure Shutdown ON ON ON ON DEFEAT See Below A B C D E Table 3 3 Rear Panel Switch Truth Table...

Page 25: ...will stop automatically on all leakage or breakdown failures For safety we recommend that you begin testing with the front panel voltage knob set at minimum E Total Defeat Full voltage is produced at...

Page 26: ...00 748 6224 Technical Assistance is available from Compliance West USA between the hours of 8 30 AM and 4 30 PM Pacific Time Compliance West USA 2120 Jimmy Durante Blvd Suite 118 Del Mar CA 92014 Phon...

Page 27: ...rvice Information The HT 10KVDC is warranted to the original purchaser for a period of 1 year This warranty does not cover problems due to misuse or neglect Malfunctions which occur within the limits...

Page 28: ...8 and 9 4 Push the red RESET button item 1 The blue TEST button will light item 2 5 Push the blue TEST button 6 The Tester will conduct a test sequence The meter will show the output voltage hold and...

Page 29: ...bilize for approximately five minutes Perform all calibration adjustments at an ambient temperature of 23 C 5 C 73 F 9 F WARNING CALIBRATION ADJUSTMENTS ARE PERFORMED ON ENERGIZED CIRCUITS EXERCISE CA...

Reviews: