20 

 
 

 

Fully automatic operation.  When Test button is pressed, the output voltage will ramp at a rate determined by the position 
of the TEST TIME adjustment knob.  Test will stop automatically on all leakage or breakdown failures. 

 

 
 

Voltage Ramp is defeated.  Same as (A) above except that full voltage is produced at the output immediately.  Test will 
stop automatically on all leakage or breakdown failures.  For safety, we recommend that you begin testing with the front 
panel voltage knob set at minimum. 

 

 

Test Timer is defeated.  Same as (A) above except that after full voltage is reached, the test will continue only as long as 
the Test button is held in, minimum one second.  Test will stop automatically on all leakage or breakdown failures. 

 

 
 

Voltage Ramp and Test Timer are defeated.  Full voltage is produced at the output immediately when the Test button is 
pressed.  The test will continue only as long as the Test button is held in, minimum one second.  Test will stop 
automatically on all leakage or breakdown failures.  For safety, we recommend that you begin testing with the front panel 
voltage knob set at minimum.  
      

 
 
 
 

Total Defeat.  Full voltage is produced at the output immediately.  Test will continue only as long as the TEST button is 
held in, minimum one second.  The HT-10KVDC will not shut down on a leakage or dielectric failure, but the front panel 
Excess Leakage or Hipot Fail lights will indicate a failure.  The Hipot Pass light will not light at the completion of a 
successful test.  For safety, we recommend that you begin testing with the front panel voltage knob set at minimum. 

WARNING:  Testing with the shutdown defeated is extremely hazardous.  The HT-10KVDC can generate lethal 
levels of voltage and current.  Therefore, care should be taken when examining the equipment being tested to 
locate areas of failure while the HT-10KVDC is operating.  Do not operate the HT-10KVDC for extended periods 
under conditions of excess leakage or dielectric breakdown, as overheating and/or damage to the equipment being 
tested may result. 

 

 

NOTE 

 
All undefined states will inhibit HT-10KVDC operation.  Buzzer will sound. 

 

Summary of Contents for HT-10KVDC

Page 1: ...HT 10KVDC Dielectric Withstand Tester 0 14000 Volts DC Output Instruction Manual COMPLIANCE WESTUSA...

Page 2: ......

Page 3: ...panel and represents the latest in high voltage laboratory testing To fully appreciate all the features of your new meter we suggest that you take a few moments to review this manual Compliance West...

Page 4: ......

Page 5: ...justment of the Leakage Current Level 14 Adjustment of the High Voltage Ramp Time 15 Adjustment of the High Voltage Level 15 Adjustment of the High Voltage Test Duration 15 Setting the Voltage Ramp Sw...

Page 6: ......

Page 7: ...e supplied cordset Turn it on using the switch on the rear panel 2 Switch the Test Duration switch on the rear panel to the DEFEAT position 3 Push the RESET Button then push and hold the TEST Button T...

Page 8: ...ost equipment However higher than normal leakage current on a particular sample may indicate an assembly or component problem in the circuit The leakage current is also monitored by the HT 10KVDC to e...

Page 9: ...d test The HT 10KVDC should remain connected to the circuit until the green Hipot Pass light or the red Hipot Fail light on the front panel is lit and the output voltage as indicated on the front pane...

Page 10: ...cuit returns output voltage to safe levels before test termination The Hipot Pass or Hipot Fail light will not light until voltage has been ramped down by the HT 10KVDC If a failure is encountered the...

Page 11: ...p ON DEFEAT Timer Duration ON DEFEAT Failure Shutdown ON DEFEAT ENVIRONMENTAL Operating Temperature 15 40 C Relative Humidity Range 0 90 non condensing GENERAL Input power requirements Model HT 10KVDC...

Page 12: ...iginal shipping container for subsequent shipping If the original shipping container is not available be sure that adequate protection is provided to prevent damage during shipment Remove the Tester f...

Page 13: ...and Rear Panel Features The front panel features of the HT 10KVDC are shown in Figure 3 1 and described in Table 3 1 The rear panel features of the HT 10KVDC are shown in Figure 3 2 and described in T...

Page 14: ...9 Figure 3 1 Controls Indicators Connectors HT 10KVDC Front Panel...

Page 15: ...l light and if not defeated the high voltage duration time starts when the voltage output reaches the preset level 5 Hipot Fail LED Indicates failure of high voltage test If arcing or a flashover of t...

Page 16: ...11 Figure 3 2 Controls Indicators Connectors HT 10KVDC Rear Panel...

Page 17: ...e test duration See Adjustment of the High Voltage Test Duration section 16 Leakage Limit Adjustment Adjusts the alarm level for the excessive leakage current test See Adjustment of the Leakage Curren...

Page 18: ...mps should be lit 10 Disconnect the black lead from the red lead and remove both leads from the HT 10KVDC 11 Enable the voltage output by pressing the RESET button then the TEST button After the full...

Page 19: ...st the Leakage Limit control item 16 on the rear panel to its maximum clockwise position 4 Make sure there are no test leads connected to the Tester 5 Push the RESET button item 1 The blue TEST light...

Page 20: ...n the Test Timer switch item 12 to the DEFEAT position The HT 10KVDC will supply voltage while the TEST button item 2 is held in 2 Make sure there are no test leads connected to the HT 10KVDC 3 Press...

Page 21: ...testing after a failure is encountered This allows the operator to find a breakdown point but all safety shutdown circuitry in the HT 10KVDC is disabled when the Failure Shutdown switch is in the DEFE...

Page 22: ...t of the circuit under test is too high the Excess Leakage LED item 3 will light and the test will terminate If the Failure Shutdown Switch is set to DEFEAT and the requirements of Table 3 3 are met t...

Page 23: ...er test result means the equipment being tested failed a test phase If unanticipated test failures continue and you suspect that the equipment under test is built correctly check the following item 1...

Page 24: ...19 Voltage Ramp ON DEFEAT ON DEFEAT DEFEAT Test Timer ON ON DEFEAT DEFEAT DEFEAT Failure Shutdown ON ON ON ON DEFEAT See Below A B C D E Table 3 3 Rear Panel Switch Truth Table...

Page 25: ...will stop automatically on all leakage or breakdown failures For safety we recommend that you begin testing with the front panel voltage knob set at minimum E Total Defeat Full voltage is produced at...

Page 26: ...00 748 6224 Technical Assistance is available from Compliance West USA between the hours of 8 30 AM and 4 30 PM Pacific Time Compliance West USA 2120 Jimmy Durante Blvd Suite 118 Del Mar CA 92014 Phon...

Page 27: ...rvice Information The HT 10KVDC is warranted to the original purchaser for a period of 1 year This warranty does not cover problems due to misuse or neglect Malfunctions which occur within the limits...

Page 28: ...8 and 9 4 Push the red RESET button item 1 The blue TEST button will light item 2 5 Push the blue TEST button 6 The Tester will conduct a test sequence The meter will show the output voltage hold and...

Page 29: ...bilize for approximately five minutes Perform all calibration adjustments at an ambient temperature of 23 C 5 C 73 F 9 F WARNING CALIBRATION ADJUSTMENTS ARE PERFORMED ON ENERGIZED CIRCUITS EXERCISE CA...

Reviews: