28
S TA R T - U P
The indicated operations must be carried out by qualified
technicians and specifically trained on the product.
Upon request, the after-sales assistance centres execute start-up.
The electric, hydraulic connections and the other work of the
system are the responsibility of the installer.
Agree the start-up date with the after-sales assistance centre with
sufficient advance
Before starting any check, verify that :
the unit is perfectly installed and in compliance with that
reported in this manual
the electric power supply line of the unit is isolated at start-
up
the isolation device of the line is open, blocked and equipped
with relative signal.
make sure no tension is present
After turning off the power, wait at least 5 minutes before
accessing to the electrical panel or any other electrical
component.
Before accessing check with a multimeter that there are no
residual stresses.
UV-C lamps
Option
Caution
Direct radiation device: causes eye irritation and skin rashes.
Any maintenance operation must be carried out with the
lamps off.
Preliminary checks
For details refer to the various chapters in the manual.
Unit OFF power supply
1 safe access
2 functional spaces
3 air flow: correct return and supply (no bypass, no
stratification)
4 integrity of structure
5 fans turn freely
6 unit on anti-vibration devices
7 condensate drain
8 air filters present and clean
9 completed aeraulic system
10 cooling circuit visual control
11 earth connection
12 power supply features
13 electric connections by customer
Summary of Contents for CSRN-XHE2 Series
Page 1: ...CSRN XHE2 49 4 110 4 R 410A M07V40B13 07 11 20 MANUAL FOR INSTALLATION USE AND MAINTENANCE...
Page 75: ...Dimensional drawings 75...
Page 77: ...Dimensional drawings 77...
Page 79: ...Dimensional drawings 79...
Page 81: ...Dimensional drawings 81...
Page 83: ...Dimensional drawings 83...
Page 85: ...Dimensional drawings 85...
Page 87: ...Dimensional drawings 87...
Page 89: ...Dimensional drawings 89...
Page 91: ...Dimensional drawings 91...