Installation Guide_PV-ezRack_SolarTerraceII-A_AU_V2.0
1/10 Duerdin Street, Clayton VIC 3168 Australia
Tel: +61 3 9239 8088 Fax: +61 3 9239 8024
E-mail: [email protected] www.clenergy.com.au
18
page
of 21
Installation Instruction
Step 4 Maintain 18mm vertical gap and
18mm horizontal gap between the two
adjacent rows of PV Modules. You can use
two Inter Clamps as separation between
two PV Modules, and remove them after
installation finished as shown in right
Figure.
Step 5 Repeat above steps to install all PV
Modules. Fasten all End Clamps and Inter
Clamps tightly with18~20N.muntil all PV
Modules are properly installed.
-Solution 2 (Apply Universal Clamps)
Step 1 Twist the head of Universal Clamp
to change functionality from end to inter
clamp as shown in right figure.
18
18
NOTE: Properly apply the Universal Clamp C-U/30/46 or Universal Clamp with Grounding Clip
C-U/30/46-G according to 5.8.1. Deployment of Grounding Clip.
Step 2 Incline the Universal Clamp to fit the channel on its lower part against the lower channel of T
Rail, and press down the Universal Clamp towards the other side to fit the channel on its upper part
against the upper channel of T Rail as shown in figure below .
Note: before installation, make sure there will be enough clearance between screw and module of
Universal Clamp as shown in figure below .
90°
Fig. 22
Fig. 23
Fig. 24