Installation Instruction
5.5 Double Support Installation
Place the double support (pre-assembled) into post head. Connect the tubes of the support the to the post
braces on the post using the M12 bolt and nut supplied
.
Recommended torque:
M12 : 40-45N·m
Note:
①
The lengths of the two tubes are different.
Make sure the shorter one is positioned at the
lower part of the tilt as shown.
②
Connect the shorter Tube Support to post
brace.
③
Adjust the bolt position of T head to align
the post brace to the Tube Support
.
④
Rotate the orientation of T head to fit the
Tube Support to the post brace.
Fig. 8
Fig. 9
Fig. 10
Fig. 11