Installation Guide_PV-ezRack_SolarTerraceII-A_AU_V2.0
1/10 Duerdin Street, Clayton VIC 3168 Australia
Tel: +61 3 9239 8088 Fax: +61 3 9239 8024
E-mail: [email protected] www.clenergy.com.au
19
page
of 21
Installation Instruction
Step 4 When using as Inter Clamp, click Universal
Clamp into the channel of T Rail and then slightly
lift the framed PV Module to make sure the
Grounding Clip of Universal Clamp will be fully
covered as shown in right Figure.
Step 3 Place the first PV Module on the T Rails and apply the Universal Clamp in the End Clamp
position to fix it and then fasten slightly with Allen Key. Make sure the frame of PV Module is fully in
contact with the Universal Clamp as shown in figure below. Visually check the Universal Clamp and
PV module are properly installed.
Step 5 Slightly place the next framed PV Module
into the other side of Universal Clamp, Making
sure the Grounding Clip of Universal Clamp will
be fully covered and the frame of PV Module is
closely in contact with Universal Clamp as shown
in right Figure.
20
Fig. 25
Fig. 26
Fig. 27