Steps:
4-
Hold the sling to the eyebolts, raise the Charge point and placed on the final location.
5-
Screw the 4 x M16 nuts with washers on the threaded rods already installed on the base (on
both sides),
replace the isolation top hat seal with the one provided to assure IP (the tightening
torque has to be 3.5 Nm)
, place again the unit cover, connect the 3G antenna connector, courtesy
light connector and the exhaust fan connector and assembly the decorative front panel.
Note:
Do not remove the eyebolts from the Charge point, leave it under the cover.
< 60º
> 550 mm
Step 4
Step 5
28
Raption
Installation Guide
Summary of Contents for Raption 100
Page 1: ...Raption Series INSTALLATION GUIDE M186A01 03 21D...
Page 2: ...2 Raption Installation Guide...
Page 15: ...15 Installation Guide Raption...
Page 16: ...3 A Dimensions Units specified in millimeters 16 Raption Installation Guide...
Page 56: ...56 Raption Installation Guide...
Page 58: ...58 Raption Installation Guide...
Page 59: ...59 Installation Guide Raption...