Table 3-13 Tools Required for Conductor Termination
Choose the conductor size and material for the inverters according to the
following configuration table:
Table 3-14 Cable Specifications
Terminal
Cable
DC input (
﹢
/
﹣
)
Standard wire box
Screw Clamp Fuse Holder: 12 - 6AWG (Copper only)
DC input (
﹢
/
﹣
)
Centralized Wire-
box
Busbar, M10 bolts: 500kcmil CU/AL. Max. (1
termination per pole), 300kcmil CU/AL Max. (2
terminations per pole) *Lugs not supplied.
* Use 5/16 or 3/8” tubular lug sized for the application.
Ground terminals
12 – 6AWG
Figure 3-28 connect the DC cable (Check the POLARITIES)
3.3.5 Communication Connection
Tools
Remark
No. 2 Phillips bit and a
Torque driver
PV String connections (Standard wire-box)
PV output conductor connections
(Centralized wire-box)
Diagonal pliers
Cut cable
Wire stripping pliers
Remove jacket
L1
L2
L3
Summary of Contents for CPS SCH Series
Page 2: ......
Page 4: ......
Page 43: ...39 Figure 3 25 AC Output Cable Connection Distributed Wire box L1 L2 L3 ...
Page 45: ...41 Figure 3 27 AC Output Cable Connection Centralized Wire box Ver 2 ...
Page 58: ...54 Figure 4 1 System setting ...
Page 81: ...77 5 4 2 6 Others The REF column is reference to Table 5 7 Enable functions ...