ZP3 Fire Panel User Guide
35
Caution:
Before testing the operator must be aware both of the operation of all
devices fitted to any auxiliary circuits and the consequences of their operation.
For example a connection to call the fire brigade.
Do the following checks every week:
1. Make sure you have contacted the alarm-receiving centre informing them of
this test.
2. Check that all LEDs are operational by carrying out a lamp test.
The zones should be varied each month to ensure that they are all tested
over time. The manual call points and fire detectors should be tested on a
rotating basis so that all devices are checked at least once during a three-
month period.
To operate a manual call point use the test key provided. To operate a
detector, use a smoke generator or heat source as appropriate for the type of
detector.
3. Operate at least one device (fire sensor or call point) in each zone.
4. Make sure that the associated sounders operate.
5. Make sure that the alarm was received at the remote manned centre (if
applicable).
6. Make sure that the device triggers the operation of any auxiliary equipment (if
applicable)
7. Accept the alarm, and press the Silence Alarms button, make sure that the
sounders silence.
8. Reset the system.
9. Make sure that the fire alarm events are recorded correctly on the ZP3 panel
printer (if installed).
10. Make sure the printer (if installed) has sufficient paper, that the print ribbon is
not dry and that the paper feeds correctly.
Note:
If any defects are discovered during routine testing, they should be
recorded in the logbook (see document 503-1842ZE-0-02). The fault must be
corrected.