1 - INTRODUCTION

Prior to the initial start-up of the 30HXC units, the people involved 

in the on-site installation, start-up, operation and maintenance of 

this unit should be thoroughly familiar with these instructions and 

the specific project data for the installation site.

The 30HXC liquid chillers are designed to provide a very high 

level of safety during installation, start-up, opera tion and 

maintenance. They will provide safe and reliable service when 

operated within their application range.

This manual provides the necessary information to familiarize 

yourself with the control system before performing start-up 

procedures. The procedures in this manual are arranged in the 

sequence required for machine installation, start-up, operation 

and maintenance.

Be sure you understand and follow the procedures and safety 

precautions contained in the instructions supplied with the 

machine, as well as those listed in this guide.

To find out, if these products comply with European directives 

(machine safety, low voltage, electromagnetic compatibility, 

equipment  under  pressure  etc.)  check  the  declarations  of 

conformity for these products.

1.1 - Installation safety considerations

Access to the unit must be reserved to authorised personnel, 

qualified and trained in monitoring and maintenance. The access 

limitation device must be installed by the customer (e.g. cut-off, 

enclosure).

After the unit has been received, when it is ready to be installed 

or reinstalled, and before it is started up, it must be inspected for 

damage.  Check  that  the  refrigerant  circuit(s)  is  (are)  intact, 

especially that no components or pipes have shifted (e.g. following 

a shock). If in doubt, carry out a leak tightness check and verify 

with the manufacturer that the circuit integrity has not been 

impaired. If damage is detected upon receipt, immediately file a 

claim with the shipping company.

Carrier strongly recommends employing a specialised company 

to unload the machine.

It is compulsory to wear personal protection equipment. 

Do not remove the skid or the packaging until the unit is in its 

final position. These units can be moved with a fork lift truck, 

as long as the forks are positioned in the right place and direction 

on the unit.

The units can also be lifted with slings, using only the designated 

lifting points marked on the unit.

Use slings or lifting beams with the correct capacity, and always 

follow the lifting instructions on the certified drawings supplied 

with the unit. Do not tilt the unit more than 15°.

Safety is only guaranteed, if these instructions are carefully 

followed.  If  this  is  not  the  case,  there  is  a  risk  of  material 

deterioration and injuries to personnel.

Never cover any protection devices.

This applies to the relief valves (if used) in the refrigerant or 

heat transfer medium circuits, the fuse plugs and the pressure 

switches.

Ensure that the valves are correctly installed, before operating 

the unit.

Classification and control 

In accordance with the Pressure Equipment Directive and 

national usage monitoring regulations in the European Union 

the protection devices for these machines are classified as follows:

Safety 

accessory*

Damage limitation accessory** 

in case of an external fire

Refrigerant side

High-pressure switch

x

External relief valve***

x

Rupture disk

x

Fuse plug

x

Heat transfer fluid side

External relief valve

****

****

*  Classified for protection in normal service situations.

**  Classified for protection in abnormal service situations.

***  The instantaneous over-pressure limited to 10% of the operating pressure 

does not apply to this abnormal service situation. The control pressure can be 

higher than the service pressure. In this case either the design temperature or 

the high-pressure switch ensures that the service pressure is not exceeded in 

normal service situations.

****  The classification of these relief valves must be made by the personnel that 

completes the whole hydronic installation.

If the relief valves are installed on a change-over valve, this is 

equipped with a relief valve on each of the two outlets. Only one 

of the two relief valves is in operation, the other one is isolated. 

Never leave the change-over valve in the intermediate position, 

i.e. with both ways open (bring the actuator in abutment, front 

or back according to the outlet to isolate). If a relief valve is 

removed for checking or replacement please ensure that there 

is always an active relief valve on each of the change-over valves 

installed in the unit.

All factory-installed relief valves are lead-sealed to prevent any 

calibration change. 

The external relief valves and the fuses are designed and installed 

to ensure damage limitation in case of a fire. 

In accordance with the regulations applied for the design, the 

European directive on equipment under pressure and in 

accordance with the national usage regulations:

 

These relief valves and fuses are not safety accessories but 

damage limitation accessories in case of a fire,

 

The high pressure switches are the safety accessories.

The relief valve must only be removed if the fire risk is fully 

controlled and after checking that this is allowed by local regulations 

and authorities. This is the responsibility of the operator.

Summary of Contents for 30HXC Series

Page 1: ...INSTALLATION OPERATION AND MAINTENANCE INSTRUCTIONS Screw Compressor Water Cooled Liquid Chillers 30HXC 080 375 Original instructions Nominal cooling capacity 30HXC 286 1300 kW 50 Hz 60Hz...

Page 2: ...nsing temperature options 150 150A 19 5 4 Physical data 30HXC option 61 380V 3ph 60Hz 20 5 5 Electrical data 30HXC option 61 21 5 6 Electrical data 30HXC option 61 with high condensing temperature opt...

Page 3: ...0 11 MAIN OPTIONS AND ACCESSORIES 41 11 1 Compressor suction valves option 92 42 11 2 Electric protection level of the 30HXC control boxes to IP44C option 20 42 11 3 Tropicalised control box for 30HXC...

Page 4: ...unit more than 15 Safety is only guaranteed if these instructions are carefully followed If this is not the case there is a risk of material deterioration and injuries to personnel Never cover any pro...

Page 5: ...r pressure The units are intended to be stored and operate in an environment where the ambient temperature must not be less than the lowest allowable temperature indicated on the nameplate See section...

Page 6: ...omplywiththeF GasDirectiveN 517 2014andanyother applicable local legislation 2 Ensure that the refrigerant is never released to the atmosphereduringinstallation maintenanceorequipment disposal 3 The d...

Page 7: ...for the system and the refrigerant type used must be within easy reach Do not siphon refrigerant Avoid contact with liquid refrigerant on the skin or splashing it into the eyes Use safety goggles Was...

Page 8: ...ATTENTION No part of the unit must be used as a walk way rack or support Periodically check and repair or if necessary replace any component or piping that shows signs of damage The refrigerant lines...

Page 9: ...rams During the installation test national regulations must be followed If no national regulation exists standard EN 378 can be used as a guide External visual installation checks Ensure that the mach...

Page 10: ...r to the certified dimensional drawings supplied with the unit when designing an installation 30HXC 080 30HXC 090 30HXC 100 30HXC 110 A D B 600 500 4 700 4 3 C E 3 3 F 1 2 Legend All dimensions are in...

Page 11: ...imensional drawings supplied with the unit when designing an installation 4 2 E 500 B 3 A C D 700 3 4 500 3 F 1 Legend All dimensions are in mm Evaporator Condenser Clearances required for operation a...

Page 12: ...nces for air flow as follows Top do not restrict in any way In case of multiple chillers up to four units the respective clearance between them should be increased from 1830 to 2000 mm for the side sp...

Page 13: ...nimum step capacity 19 19 21 19 21 19 17 19 21 21 14 14 14 14 10 10 10 Evaporator Shell and tube with internally finned copper tubes Net water volume l 50 50 58 69 65 65 75 75 88 88 126 155 170 170 19...

Page 14: ...io circuit A 3 02 3 13 2 79 2 99 2 96 2 79 2 99 Max starting current max current draw ratio circuit B 4 70 4 58 4 58 4 97 2 96 2 79 2 99 Max starting current reduced current start Un A std std std std...

Page 15: ...B A 161 189 189 235 350 377 469 Maximum starting current standard unit Un A 281 316 338 382 404 437 521 548 576 635 1255 1549 1603 1734 1737 1792 1969 Circuit A A 1094 1360 1415 1500 1387 1415 1500 Ci...

Page 16: ...cal to those of the standard 30HXC units The only difference is in the diameter of the incoming field wiring connection described in the chapter Recommended selection Refer to the dimensional drawings...

Page 17: ...19 21 19 17 19 21 21 14 14 14 14 10 10 10 Evaporator Shell and tube with internally finned copper tubes Net water volume l 50 50 58 69 65 65 75 75 88 88 126 155 170 170 191 208 208 Water connections V...

Page 18: ...87 1 91 Max starting current max current draw ratio circuit A 2 88 3 04 2 73 2 83 2 88 2 73 2 83 Max starting current max current draw ratio circuit B 4 45 4 46 4 46 4 66 2 88 2 73 2 83 Max starting c...

Page 19: ...2 24 Max starting current max current draw ratio circuit A 3 56 3 52 3 11 3 48 3 32 3 11 3 48 Max starting current max current draw ratio circuit B 5 66 5 23 5 23 5 96 3 32 3 11 3 48 Max starting curr...

Page 20: ...10 10 Evaporator Shell and tube with internally finned copper tubes Net water volume l 50 50 58 69 65 65 75 75 88 88 126 155 170 170 191 208 208 Water connections Victaulic connections Inlet outlet i...

Page 21: ...77 1 81 Max starting current max current draw ratio circuit A 2 67 2 81 2 54 2 63 2 67 2 54 2 63 Max starting current max current draw ratio circuit B 4 06 4 08 4 08 4 25 2 67 2 54 2 63 Max starting...

Page 22: ...std std std std std std std 1 62 1 64 1 57 1 68 1 47 1 42 1 51 Circuit A 1 96 2 01 1 85 2 01 1 93 1 85 2 01 Circuit B 2 29 2 04 2 04 2 52 1 93 1 85 2 01 Three phase short circuit holding current kA 2...

Page 23: ...n range allows the production of glycol water solution down to 10 C with ethylene glycol at 35 by weight or down to 7 C with propylene glycol at 30 by weight The precision of these amounts is critical...

Page 24: ...eration permitted but performances is not optimized Condenser entering water temperature C Condenser entering water temperature C Evaporator leaving water temperature C 50 48 44 20 15 13 D C 7 0 4 13...

Page 25: ...evaporator is equipped with heat insulation of 38 mm thick polyurethane foam Cooler pressure drop 30HXC low brine version Pure water flow rate l s Pressure drop kPa 0 01 0 1 1 10 100 1000 1 10 100 HXC...

Page 26: ...ing temperature 50 C at full load 4 For low evaporator leaving temperatures 4 C and 6 C order option 5 Legend A Standard unit operating at full load B Standard unit operating at reduced load C Units o...

Page 27: ...ary for stable operation and accurate temperature control It is often necessary to add a buffer water tank to the circuit in order to achieve the required volume The tank must itself be internally baf...

Page 28: ...ser pressure drop curve Pressure drop kPa Water flow rate l s Note The dotted part of the curves corresponds to the flow values only permitted for closed circuits Legend 1 30HXC 080 090 100 110 2 30HX...

Page 29: ...ble section see table Recommended wire sections 30HXC A B C D E F G H Standard Circuit A 310 375 400A 56 25 4 1492 6 314 1824 314 10 5 Circuit B 310 345 400A 56 25 4 1492 6 314 1824 314 10 5 375 630A...

Page 30: ...s disconnect switches and branch sections designed to supply the evaporator and condenser pump power input IMPORTANT Generally the recommendations of IEC 60364 are accepted as compliance with the requ...

Page 31: ...IMPORTANT Before connection of the main power cables L1 L2 L3 on the terminal block it is imperative to check the correct order of the 3 phases before proceeding to the connection on then terminal blo...

Page 32: ...itches are indicated by a 1 8 4 3 Selection table of minimum and maximum wire sections 400V 3ph 50Hz option 150 30HXC Minimum wire section mm2 Wire type L m Maximum wire section mm2 Wire type L m 080...

Page 33: ...E Al 265 2 x 95 XLPE Cu 270 375 Circuit A 1 x 150 XLPE Cu 190 2 x 185 XLPE Al 270 2 x 120 XLPE Cu 280 200 Circuit B 1 x 50 XLPE Cu 160 1 x 120 XLPE Al 205 1 x 70 XLPE Cu 205 230 Circuit B 1 x 70 XLPE...

Page 34: ...u 190 2 x 240 XLPE Cu 295 Power supply wire section see diagram in chapter Electrical connection 8 4 6 Selection table of minimum and maximum wire sections 380V 3ph 60Hz option 61 30HXC Minimum wire s...

Page 35: ...PE Cu 190 2 x 185 XLPE Al 270 1 x 240 XLPE Cu 235 260 Circuit A 1 x 240 XLPE Cu 190 2 x 240 XLPE Al 280 2 x 150 XLPE Cu 290 285 Circuit A 1 x 240 XLPE Cu 190 2 x 240 XLPE Cu 295 310 Circuit A 1 x 185...

Page 36: ...any start up verify that the heat exchange fluid is compatible with the materials and the water circuit coating In case additives or other fluids than those recommended by Carrier are used ensure tha...

Page 37: ...second B Initialisation validation Release the button for between 1 and 5 seconds C Threshold control Press for the number of seconds that corresponds to the required setpoint pressing for 10 seconds...

Page 38: ...ator flow stopped to allow safe pressure equilibrium Special attention has to be given to the hydraulic design when option 152 is selected in order to maintain the condenser flow even when the 0 10V s...

Page 39: ...se a flooded evaporator The water circulates in the tubes and the refrigerant is on the outside in the shell One vessel is used to serve both refrigerant circuits There is a center tube sheet which se...

Page 40: ...oint on until the initialization the processor counts the total number of open and closed steps it has sent to each valve 10 4 Economizer Economizers are installed on 30HXC 190 285 and 375 The economi...

Page 41: ...um water side service pressure to 21 bar standard 10 bar Covers applications with a high water column condenser side typically high buildings 080 375 Reversed evaporator water connections 107 Evaporat...

Page 42: ...get the best performance from your HVAC unit improved cooling performance reduced power consumption prevention of accidental component failure prevention of major time consuming and costly interventio...

Page 43: ...rsunder normal operation The 30HXC metering device is designed to work properly under these conditions 1 Make sure that the circuit is running at a full load condition TocheckwhethercircuitAisfullyloa...

Page 44: ...sor 2 Manually force the operation of the oil solenoid valve in order to press the internal valve shutter onto its seat 3 Close the oil filter service valve Bleed pressure from the filter cavity throu...

Page 45: ...the bottom of its stroke If it is believed that the valve is not working properly contact your Carrier service department for further checks on output signals on EXV module wire connections continuity...

Page 46: ...Additional air handling units and accessories Preliminary equipment check Is there any shipping damage If so where Will this damage prevent unit start up Unit is level in its installation Power supply...

Page 47: ...power company for assistance All incoming power voltage is within rated voltage range Check cooler water loop Water loop volume litres Calculated volume litres 3 25 litres nominal kW capacity for air...

Page 48: ...t Condenser water sensors Water valve type If installed To start the chiller WARNING Be sure that all service valves are open and all pumps are on before attempting to start this machine Once all chec...

Page 49: ......

Page 50: ...es order No 13050 03 2011 Manufacturer Carrier SCS Montluel France Manufacturer reserves the right to change any product specifications without notice Printed in the European Union www eurovent certif...

Reviews: