Viento - Installation/Rev- #33/54
3 hoses have to be connected to the evaporator :
-
Suction pressure hose
: from the CRP valve outlet
(
∅
16 – module 12) to the compressor.
-
Liquid line hose
: from the expansion valve
through the heat exchanger (
∅
8 – module 6) to the
host unit.
-
Hot gas line
: from the defrost element inlet
(
∅
8 – module 6) to the host unit.
1. Run hoses and harness through the hole.
- Suction line
- Liquid line
- Hot gas line
- Fan motor wires
- RAT cable
- Injection valve if so equipped
2. Prepare hoses as described in section "Unit hoses /
Preparation - p25".
Installation Evaporator connection
Refrigeration hoses