MCBF
Models
BKX12
20 m - 1200 kg
250.000
Full leaf
-15%
Installation in windy area
-15%
Full leaf installed in windy area
-30%
The percentages indicate how much the number of cycles should be reduced in relation to the type and number of accessories installed.
Before carrying out any cleaning or maintenance, or replacing any parts, disconnect the device from the power supply.
This document informs the installer of the checks that must be carried out during maintenance.
If the system is not used for long periods of time, e.g. for installations at sites with seasonal closures, disconnect the power supply. When the power supply is
reconnected, check the system is working correctly.
For information on correct installation and adjustments, please see the product installation manual.
For information on choosing products and accessories, please see our product catalogue.
Every 10,000 cycles and, in any case, every 6 months of operation, you must perform the maintenance work indicated below.
Perform a general and complete check of the tightness of the nuts and bolts.
Grease all of the moving mechanical parts.
Check the warning and safety devices are working properly.
Check for any wear on the moving mechanical parts and check that they are working properly.
Check the release mechanism is working efficiently by performing a manoeuvre with the leaf free. The gate leaf must not be obstructed.
Check the cables are intact and connected correctly.
Check and clean the slide guide and rack.