Chapter 4: Preparing for installation
Testing system components
Page
4-9
Equipment to Be
Installed
Tools Required
AP or BHM or BHS
Antenna
•
13 mm Spanner Wrench (or Ratchet Spanner Wrench) Pair
Used for connecting the antenna (sector or omni for AP, or directional for
BH) base to the pole/mast mounting bracket
•
Self-amalgamating and PVC Tape
Used for weatherproofing N-type connections
•
N-type Torque Wrench (not required but recommended)
Used for assuring proper tightening of N-type connectors terminating the
RF cables
SM
•
Wrench/driver (depending on operator’s choice of clamps)
Used for tightening clamps to the pole
•
Alignment tone adapter / headset
Used for aligning the SM to the AP
Universal Global
Positioning System
•
Philips Screwdriver
Used for attaching the UGPS unit to the pole/mast mounting bracket
•
13mm Spanner Wrench (or Ratchet Spanner Wrench)
Used for connecting the mounting bracket’s U-bolt to the antenna or mast
Cabling
•
Electrician’s Scissors or Wire Cutters
Used for cutting wire to length
•
RJ-11/RJ-45 Crimping Tool
Used for stripping RJ-11/RJ-45 cables and for terminating cable ends
•
Cable Testing Device
Used to ensure that cables are properly constructed
Standards for Wiring
Modules automatically sense whether the Ethernet cable in a connection is wired as straight-through or
crossover. Operators may use either straight-through or crossover cable to connect a network interface
card (NIC), hub, router, or switch to these modules. This guide follows the EIA/TIA-568B colour code