background image

Noise emission

Refer to the table “Technical data” for permissible noise levels in free
field conditions according to EN ISO 2151.

CAUTION

The sound level of the vacuum pump within a certain perimeter of
the pump is high.

Risk of hearing damage.

Users who are spending a longer period of time in the vicinity of a
non-insulated vacuum pump must wear suitable ear protection.

Safety area

Before any maintenance action, ensure a safety perimeter of at least
1 [m] around the pump.

Stopping procedure for maintenance

l

Apply an inlet pressure between atmospheric pressure and 650 hPa
(abs.) in order to guarantee that the outlet gas temperature does
not exceed 80°C.

l

Close the injection of cooling liquid (INJ) in the cylinder

u

Let the vacuum pump run for 1 minute

l

Stop the vacuum pump

l

Close the cooling liquid supply (CL)

l

Switch off power supply (the vacuum pump must be fully discon-
nected from any power supply)

l

Put up label or warning board “Maintenance in progress” on or
next to the pump.

Start-up procedure after maintenance

l

Remove label or warning board “Maintenance in progress”

l

Check oil level according to the chapters “Checking the oil level”

l

Switch on power supply (the vacuum pump must be connected to
the power supply)

l

Check that the “Installation prerequisites” are observed

l

Open the cooling liquid supply (CL)

u

Adjust the flow rate to 12 l/min

l

Start the vacuum pump

l

Open the injection of cooling liquid in the cylinder (INJ)

u

With the pump operating at 60 Hz/3600 rpm and an inlet
pressure < 100 mbar. Adjust the cooling liquid flow rate to
6 l/min or a quantity sufficient to ensure an exhaust gas outlet
temperature <80°C

l

Check the exhaust gas outlet temperature <80°C

l

If the vacuum pump is equipped with a solenoid valve at the inlet:

u

Open the solenoid valve

l

If the vacuum pump is equipped with a shut-off valve at the inlet:

u

Open the shut-off valve

Transport

The COBRA vacuum pumps are tested and checked in our factory
before careful packing. Check the packaging for transport damage
when the goods arrive. The pump can withstand temperatures
between -25°C and +55°C during transport.

Transportation of packaged pump

Packed on a pallet, the vacuum pump can be transported with a
forklift.

Transport in unpacked state

The vacuum pump is bolted to a pallet or a base plate:

u

Remove the bolts between the vacuum pump and the pallet or
base plate

CAUTION

Do not walk, work or stand under suspended loads.

CAUTION

Please check out the weight of the vacuum pump before lifting it up
(see “Technical Data”).

Use adequate lifting gear for this.

NOTE

: The eyebolts are not used to lift the vacuum pump from the

packing. The vacuum pump must be lifted by the base frame (with a
forklift or belts).

l

Attach belts securely to the base frame

l

Use lifting gear with a crane hook equipped with safety latch.

l

Lift the vacuum pump

In case the vacuum pump was bolted to a pallet with fixing bolts:

u

Unscrew the fixing bolts in the base frame

CAUTION

Once filled with oil, the vacuum pump cannot be lifted anymore.

Prior to every transport, make sure that the oil has been drained from
the vacuum pump

The packaging material must be disposed of in accordance with local
and national regulations.

This operating instructions is part of the delivery package.

Storage

Short-term Storage

l

Make sure that the inlet/ discharge connections are closed (leave
the provided plugs in the pump)

l

Store the vacuum pump

if possible in its original packaging,

indoors,

dry,

in a dust free room and

free from vibrations

Removal from storage

Before starting up a vacuum pump that has been stored outside the
building for a while, the vacuum pump must be moved to a room with
ambient temperature, where it should rest for a day.

Conservation

In case of adverse ambient conditions (e.g. aggressive atmosphere,
frequent temperature changes) conserve the vacuum pump
immediately.
In case of favourable ambient conditions conserve the vacuum pump if
a storage of more than 3 months is anticipated.

l

Make sure that all openings are hermetically sealed; use adhesive
tape to fasten loose parts (such as o-rings, flat seals, etc.).

Transport
Page 6

Summary of Contents for COBRA AC 1000 F

Page 1: ...e Instructions Screw Vacuum Pumps COBRA AC 1000 F VR Vapour Recovery ATEX version II 2G i o IIB T4 X Ateliers Busch S A Zone industrielle 2906 Chevenez Switzerland 0870561056 180809 Original instructi...

Page 2: ...First start up of the system 13 Switching off the system 13 Re start procedure following an Emergency Shut Down of the system 14 Maintenance 14 General information 14 Maintenance program 15 Weekly 15...

Page 3: ...g liquid inlet connection CLO Cooling liquid outlet connection OFP Oil filler plug OSG Oil sight glass ODV Oil drain ball valve MP Magnetic plug DV1 Ventilation G1 4 DV2 Aeration valve CLD Cooling liq...

Page 4: ...g liquid injection in the cylinder The COBRA vacuum pumps the principle of screw pumps Two parallel screws RT rotate in opposite directions in the pump body Entering gases are trapped between the pitc...

Page 5: ...l accordingly Local regulations regarding the motors and electric control elements must be observed when installing the pump in potentially explosive environments The maintenance instructions must be...

Page 6: ...careful packing Check the packaging for transport damage when the goods arrive The pump can withstand temperatures between 25 C and 55 C during transport Transportation of packaged pump Packed on a p...

Page 7: ...pe corresponds to the ambient conditions see Oil type Ambient pressure atmospheric Humidity range 20 to 95 Altitude up to 1000 m l Make sure that the cooling liquid fulfills the following require ment...

Page 8: ...scharge lines the line cross section should be larger than the exhaust flange in order to prevent a drop in the performance of the vacuum pump If you have any doubts contact your Busch representative...

Page 9: ...or PSA 0301 The sensor must be connected in such a way that the vacuum pump stops when the counter pressure reaches the value prescribed in the COBRA ATEX catalogue Technical data of the standard prod...

Page 10: ...meter FSA 0502 The contact flow meter must be connected in such a way that the vacuum pump stops when the flow drops below 2 l min It is possible to run the vacuum pump with an injection liquid flow o...

Page 11: ...talogue If the unit motor coupling hub is already fitted u Move the coupling hubs on the shafts in order to reach value E see COBRA ATEX catalogue l Lock the coupling hubs by tightening the set screws...

Page 12: ...t the cooling liquid inlet CLI and outlet CLO connections l Open the cooling liquid supply l Adjust the cooling liquid flow to 12 l min Connection of the injection liquid into the cylinder INJ NOTE Ma...

Page 13: ...e that the Installation Prerequisites are complied with and will remain so and ensure that adequate cooling is guaranteed If the pump is shut down for a longer period of time CAUTION If there is a ris...

Page 14: ...ations given below WARNING The inside of the vacuum pump must regularly be checked for de posits and be cleaned as and when necessary for example by pur ging the pump Deposits can cause friction and s...

Page 15: ...eaks have the vacuum pump repaired Busch service l Check the vacuum pump for cooling liquid leaks in case of leaks have the vacuum pump repaired Busch service In case of operation in a dusty environme...

Page 16: ...ler plugs OFP l Top up with oil l Make sure that the oil level is on MAX mark of the oil sight glass l Make sure that the seal of the oil filler plug are not damaged and replace plug if necessary l Re...

Page 17: ...ing liquid in compliance with applicable re gulations Checking the current consumption l Check the current of the motor An increased current indicates a fault see Troubleshooting Checking the motor ho...

Page 18: ...es must be disposed of separately in compliance with applicable environmental regulations When the vacuum pump comes to the end of its life it must be decontaminated CAUTION Only authorised personnel...

Page 19: ...artial clogging in the suction discharge or pressure line Remove the clogging Long suction discharge or pressure line with too small diameter Use larger diameter Internal parts worn or damaged Repair...

Page 20: ...ral weeks or months Let the vacuum pump run warm with inlet closed Oil viscosity is too high for the ambient tempe rature Use oil with a better viscosity class Improper oil quantity unsuitable oil typ...

Page 21: ...ge intervals are too long The oil was overheated Drain oil Fill in new oil see Maintenance In case the oil life is too short use oil with better heat resistance or retrofit cooling Cooling liquid flow...

Page 22: ...1 0486000766 510 O ring 2 0486511445 511 O ring 1 0486000645 512 O ring 2 0486000526 513 O ring 2 0486000636 514 O ring 2 0486000538 515 Shaft seal 1 0487553116 516 Seal 2 0486511080 732 Flat seal 1 0...

Page 23: ...ellus S2 V 68 High Performance hydraulic oil viscosity class ISO HC 68 20 60 C TOTAL AZOLLA ZS 68 viscosity class ISO VG 68 Oil quantity The quantity of oil specified in the following table is of info...

Page 24: ...l motor speed 50 Hz 60 Hz min 1 min 1 3000 3600 Noise level EN ISO 2151 50 Hz 60 Hz dB A dB A 83 85 Ambient temperature C 20 40 Ambient temperature high temperature version refer to the pump nameplate...

Page 25: ...tances to prevent hazard zones being reached by the upper and lower limbs EN 1012 1 2010 EN 1012 2 1996 A1 2009 Compressors and vacuum pumps Safety requirements Part 1 and 2 EN ISO 2151 2008 Acoustics...

Page 26: ...Note...

Page 27: ...Note...

Page 28: ...Majang myun Icheon si Gyunggi do 467 813 Republic of Korea Phone 82 31 645 2700 Fax 82 31 631 2898 e mail busch busch co kr Malaysia Busch Malaysia Sdn Bhd 4 6 Jalan Taboh 33 22 Seksyen 33 Shah Alam T...

Reviews: