70
We reserve the right to make any changes due to technical modifications!
Installation and Servicing Instructions Logamax plus GB142-24/30/45/60 • Version 12/2004
Buderus Hydronic Systems • http://www.buderus.net
Servicing
14
z
Fit the cover on the external connection box (see
fig. 93).
z
Fit the casing.
z
Connect the heating system to the power supply,
insert the main fuse or switch on the circuit breaker.
z
Set the main switch on the BC10 to "1" (On).
14.23 Transformer; checking and if
necessary replacing
z
Disconnect the heating system from the power
supply, remove the main fuse or switch off the circuit
breaker.
z
Set the main switch on the BC10 to "0" (Off).
z
Remove the casing.
z
Dismantle the cover of the external connection board
(see fig. 94).
z
Pull the 4 plugs from the external connection board
(see fig. 95, pos. 1, 2, 3 and 4).
Fig. 93
Installing the cover of the connection box
Fig. 94
Dismantling the cover of the external connection
board
Fig. 95
Pulling the external connection board plug
2
1
4
3