5.1.
Foundation Base
When preparing the foundation base and cabling pay regard to positions of cable through
holes and expansion bolts.
5.1.1.
Input Terminal and Wiring Specifications:
•
Power Cable: L1(Brown), L2(Black), L3 (Gray), N(Blue) wiring M8
–
70mm
2
/ L=900mm
minimum
•
Ground cable : FG(green/yellow) wiring M8 - 25mm2 / L=900mm minimum
5.1.2.
Installation Position:
•
Charger Size: 738(W) x 1884(H) x 808(D) mm
•
There are 4 fixed positions at intervals of 400mm in width and 600mm in length at the
bottom of the charger, and 4EA anchor bolts of M16 are required for foundation
construction. The length of anchor bolts protruding from the ground should not exceed
60mm.
5.2.
Space Requirement
When installing the BTCP Charger, it must be ensured to give certain a minimum distance from
possible objects around the BTCP Charger, to allow adequate airflow, and secondly, space for
possible service or maintenance operations.