OPERATION
Fig. 4 Brewer Operation Diagram
A. START-UP
For initial start-up, or if the brewer has not been used for an
extended period of time:
♦
Be sure spray disk and brew gasket are properly installed in the
brew head.
♦
Be sure the water supply is properly connected and the water
supply valve is turned
ON
.
♦
Be sure faucet water tank drain cap is securely installed.
♦
Be sure the WATER TANKS ARE FILLED.
IMPORTANT:
Fill the water tanks before pressing heater switches
ON
:
1. Insert the brew chamber (empty) and place an empty airpot in
place under the brew chamber. Be sure heater switches are
OFF
.
2. Turn main power switch
ON
.
3. Press "BREW" button and allow brew cycle to complete. Repeat
until water flows from the brew head.
4. Place an empty container under the hot water faucet. Hold the
faucet open until water flows and all air is purged.
5. Press the tank heater switches
ON
. The heating elements will
begin heating the water in the tanks. When the water in a tank has
reached the proper temperature, the associated "READY" light will
glow.
IMPORTANT:
Tanks must be full of
water before pressing
either TANK HEATER
SWITCH "
ON
". Heating
elements will be damaged
if allowed to operate
without being fully
submerged in water.
Damage caused by
operating the brewer
without water in the tank
is
NOT COVERED BY
WARRANTY
.
6