The  boiler  must  be  steadily  fixed  over  inflammable  or  heat-isolated  foundation,  which  must 
exceed the boiler contour with minimum of 300 mm in front and 100 mm in all other sides. For 
easier handling and operation it is recommended that the foundation is inflammable and 100 – 
150 mm high.  
 
The boiler room must have ensured constant air flow for burning. Air consumption depends on 
the  boiler  heating  capacity,  respectively  45-60  m

3

/h  (200-300  cm

2

  opening  for  air  intake 

corresponds to such flow).  
 

Danger 
When the boiler operates do not touch any hot water pipe lines or flue pipes. 

 
If  there  are  two  boilers  in  the  room  it  is  not  allowed  to  position  any  fuel  between  them.  It  is 
recommended  to  keep  minimum  distance  of  800mm  between  the  boiler  and  the  fuel,  or  to 
store the fuel in a premise different from the boiler room.   
 
 

 

Danger 
Do not put flammable materials over boiler’s top side or near it within the safety 
distance. 

 

7.4. CONNECTING THE BOILER TO THE HEATING SYSTEM

 

 

The BiSolid Saver boiler is designated for systems with natural gravity or forced circulation. To 
reduce condensation of flue gases and to prolong boiler’s life time it is recommended to use 
devices  which  do  not  allow  the  water  temperature  to  decrease  less  than  65 

o

C  (flue  gases 

point  of  condensation).  For  that  purpose  for  example  can  be  used  a  three-way,  four-way 
valves (DUOMIX) or thermostatic valve TSV.    
 
Clean  water  has  to  be  used  as  heat-carrier  and  it  must  comply  with  the  standards.  Its 
hardness must not exceed the required values (Table 6).     
 

Table 6. Boiler water parameters 

 

Value 

Dimension 

Value 

Hardness 

mmol/l 

Ca

2+

  

mmol/l 

0.3 

Total concentration of Fe + Mn 

mg/l 

(0.3)* 

 

* - recommended value 

 
As  a  passive  boiler  defense  can  be  used  liquids  with  low  freezing  point  and  anti-corrosion 
action, for example FRITERM. In the cases when a two-way safety valve is connected to the 
system, applying anti-freezing liquid is not recommended.  
 
 
 

Summary of Contents for Saver A

Page 1: ...NSTALLATION OPERATION AND MAINTENANCE MANUAL BiSolid Saver 31 1 2013 09 12 OM BSSV00 08 2012 EN MANUAL FOR INSTALLATION OPERATION AND MAINTENANCE OF HOT WATER SOLID FUEL BOILER FROM SERIES BISOLD SAVE...

Page 2: ...R LONG TERM SWITCH OFF 24 5 6 BOILER HANDLING 25 5 7 BOILER CLEANING AND MAINTENANCE 25 5 8 BOILER REPAIR 26 5 9 WARRANTY AND WARRANTY CONDITIONS 27 5 10 BOILER PACKAGE KIT AT DELIVERY 27 6 BOILER OPE...

Page 3: ...its accessories operate under variable electricity 220 230 V Improper electrical installation or repair may endanger user s life from electrical shock Installation works must be performed only by qual...

Page 4: ...functioning safe and long term operation of the appliance a regular check ups and prophylaxis must be performed at least once per year Such technical care guarantees your investment Repairs should be...

Page 5: ...are led to the flue pipe Under the combustion chamber and the fuel loading tank is situated a two component grill which can be easily controlled with a lever on the boiler side The primary air is sup...

Page 6: ...sh cleaning door 6 Pipes to DBV1 not standard part of the boiler delivery kit 7 DBV1 two way cooling safety valve not standard part of the boiler delivery kit 8 TRV temperature valve regulating the bo...

Page 7: ...turbolators position 6 Rear section 7 Hot water outlet 8 Flue pipe 150 mm 9 Isolation cover 10 Fireclay bricks 11 Cold water inlet 12 Draining muff 13 Cleaning cover 14 Bushes for legs 15 Bottom isol...

Page 8: ...competitor boilers is achieved due to the steel made three pass construction of the heat exchanger finishing with two sets of steel tubes larger heat exchanging area The boilers are suitable for heat...

Page 9: ...INSTALLATION OPERATION AND MAINTENANCE MANUAL BiSolid Saver OM BSSV00 08 2012 EN 9 Figure 4 Standard equipment of the boilers from series BiSolid Saver W...

Page 10: ...ion operation and maintenance The boiler complies with the European ecology directives and requirements Developed and designed for easy and quick installation of pellet burner BiSolid GP Technical dat...

Page 11: ...construction of the heat exchanger finishing with two sets of steel tubes larger heat exchanging area Outer view of hot water boiler from series BiSolid Saver is presented in Figure 5 Figure 5 Outer v...

Page 12: ...ortable for installation operation and maintenance The pellet burners from series BiSolid GP are fully automated ignition flame control combustion chamber blowing Also equipped with intuitive LCD disp...

Page 13: ...00 1100 Boiler wide mm 720 720 720 720 Up to this moment the boilers from series BiSolid Saver A have no analogue on the Bulgarian market They are equipped with constantly installed pellet burner BiSo...

Page 14: ...Solid Saver OM BSSV00 08 2012 EN 14 Figure 7 Outer view of hot water boiler BiSolid Saver Standard equipment of the boilers from series BiSolid Saver A is presented in Figure 8 Figure 8 Standard equip...

Page 15: ...e steel which guarantees reliable and long term operation Automatic modulation of the burning process decreasing the number of stops and ignitions respectively fuel and electricity consumption Possibi...

Page 16: ...BiSolid GP Description Dimension Saver 25 Saver 40 Fuel Wood Pellets Wood Pellets Wood pellets category according to EN 14961 2 ENplus A1 ENplus A1 Nominal heating output kW 25 25 40 35 Working press...

Page 17: ...rvention might damage the boiler and possibly the accompanying equipment The service technician initializing the boiler start up for first time must show the customer all of its main components differ...

Page 18: ...not be dangerously hot If there is any leakage from the boiler s heat exchanger or when the heat exchanger is choked up do not try to start the boiler until normal operation conditions are recovered 2...

Page 19: ...The ash should be taken out in fireproof container with cover Danger In case of danger from penetration of flammable vapors or gasses in the boiler room or any activities that may lead to fire or exp...

Page 20: ...ainer When handling or operating please use gloves as protective equipment Danger When installing the boiler and elements for safety and control please do not forget that all installation works must c...

Page 21: ...color no suspended particulates oils and chemically aggressive and corrosive substances and also it should not be acid pH factor must be higher than 7 0 At first place a comprehensive washing of the e...

Page 22: ...tracking the smoke out of the chimney Indication for quality burning is the lack of excessive smoke from the chimney in case it s a fact it means that there is insufficient secondary air in the combus...

Page 23: ...forms on the inside boiler walls which leak into the combustion chamber Because the flue gases condensation point is 65 o C the condensation forms only when there is cooling of the gases in the middl...

Page 24: ...must burn completely by itself over the fire grate 5 4 BOILER SHORT TERM SWITCH OFF After switching off the boiler clean it take out all burned wastes empty its ash box clean the contact surfaces of...

Page 25: ...t and efficiency We recommend that during transition seasons spring autumn the boiler should be fired for short time at full heating output in order to burn the deposits and to dry the chimney Warning...

Page 26: ...ler The yearly maintenance prophylaxis of the boiler must be performed only by authorized technicians before the start of the heating season Before calling the service technicians the user has to prov...

Page 27: ...resent it to the Seller or authorized service company 5 10 BOILER PACKAGE KIT AT DELIVERY All hot water boilers from series BiSolid Saver are delivered fully assembled and functionality tested The ful...

Page 28: ...r covers kit Sealing rope for heat exchanger cover Special requirement for spare parts must be coordinated with the manufacturer Direction When sending spare parts order please point out the boiler ty...

Page 29: ...than a minute you can switch from wood logs to wood pellets and contrariwise The burners from series BiSolid GP can burn wood pellets with diameter 6 8 mm and category of wood pellets according to EN...

Page 30: ...llet burner When operating boilers from series BiSolid Saver A with wood logs the consumers use the constantly installed pellet burner from series BiSolid GP for initial firing of the wood logs placed...

Page 31: ...pellet burner In this case before starting the pellet burner the user must change the position of the fire grates in the combustion chamber as described in Figure 11 Warning When operating with wood...

Page 32: ...ith wood logs please observe the instructions in part 5 6 from the current manual for operation When operating with wood pellets handling of the pellet burner must be performed according to the BiSoli...

Page 33: ...he electrical parts must be performed by authorized person Warning The burner must be connected to the electrical installation of the relevant appliance boiler by observing all safety techiques The ma...

Page 34: ...6 1 2 3 4 5 6 1 2 3 4 5 6 6 5 4 3 2 1 6 5 4 3 2 1 Fresh air Flue extractor optional Pump Ignition Photo sensor Start Back fire Room thermostat Pt 1000 H2O 1100 W X1 X2 X3 X4 X5 F1 2A F2 2A F3 2A F4 2A...

Page 35: ...with wood logs or wood pellets do not interrupt the boiler power supply because the circulation pump must operate until the boiler cools down In all wiring types the circulation pump must always oper...

Page 36: ...INSTALLATION OPERATION AND MAINTENANCE MANUAL BiSolid Saver OM BSSV00 08 2012 EN 36 Figure 15 Control panel with connectors for pellet burner wiring diagram Pt 1000 Connector Communication...

Page 37: ...ely water temperature sensor Pt1000 must be performed according to the scheme presented in Figure 16 Figure 16 Installation of water temperature sensor Warning Installation of the temperature sensor m...

Page 38: ...n for economic and optimum operation of the appliance The boiler has to be chosen with such size that corresponds to the heating losses of the designated building site Choice of a boiler with too high...

Page 39: ...e boiler room Danger Do not put flammable materials over boiler s top side or near it within the safety distance 7 4 CONNECTING THE BOILER TO THE HEATING SYSTEM The BiSolid Saver boiler is designated...

Page 40: ...revent the fuel feeding door to open properly 7 7 BOILER STRUCTURE INSTALLATION OF COVER PANELS Before performing the boiler installation it is necessary to check 1 Equipment a Free equipment covers w...

Page 41: ...8 d Front cover panel position 4 fig 17 has to be installed from its wider fixing side under the low body brackets then fix it with force to the boiler and then fix it to the upper brackets e Installa...

Page 42: ...ortest as possible without shut off devices and with availability for expansion The expansion tank has to be positioned without possibility for heating from sun light 2 Every heating system must be eq...

Page 43: ...ed at least once per year 12 Individual project must be designed for every heating system 13 If optimum expansion tank is chosen then should not be measured more than 60 kPa hydraulic pressure and wit...

Page 44: ...d transportation During transportation and storage the boilers packages and cover panels should not be pressed Danger The boilers should not be moved or transported without using forklifts transport c...

Page 45: ...y draught has an important effect over the boiler heating output its efficiency and life cycle length Recommended chimney heights are presented in Table 7 Table 7 Recommended chimney heights Chimney s...

Page 46: ...operation Read BiSolid GP pellet burner operation manual Unsealed fuel feeding and ash cleaning doors Check sealing ropes correct sealing ropes positioning if necessary replace sealing ropes Boiler s...

Page 47: ...INSTALLATION OPERATION AND MAINTENANCE MANUAL BiSolid Saver OM BSSV00 08 2012 EN 47 Supplier Address City Str Tel Fax http Reserved rights for technical changes...

Reviews: