5.2
Inspection before commissioning
The relevant country-specific regulations must be observed with regard to testing prior
to commissioning.
Implement a risk assessment in accordance with the applicable national guidelines.
Safety-related technical inspections must be executed in accordance with national
regulations.
NOTE
Technical safety inspection
After initial connection by a qualified electrician, a measurement of the loop
impedance of the fuse must be carried out.