Step
Action
6
The tension is correct when a force of 50 N (11.25 lbf) applied at the midpoint of the belt
causes a deflection of 6 mm (0.23 in).
7
Retighten bolts (2).
8
Refit the bodywork panels.
Belt replacement procedure
Step
Action
1
Stop the compressor, close the air outlet valve and switch off the voltage.
For Full-Feature versions: also stop the dryer.
2
Remove the front panel of the compressor housing.
3
Remove the side, back and top panels of the compressor housing.
4
Loosen the 4 bolts (2) by one turn.
5
Release the belt tension by loosening tensioning nut (1).
6
Remove the fan cowl.
7
Remove the belt via the fan cowl opening. Install the new belt via the same opening.
8
Tension belt (3) as described above.
9
Re-assemble the fan cowl.
10
Refit the bodywork panels.
11
Check the belt tension after 50 running hours.
Instruction book
56
2920 7105 31
Summary of Contents for GX 2 EP
Page 2: ......
Page 13: ...2 2 Air flow Pack Air flow floor mounted Pack units Instruction book 2920 7105 31 11 ...
Page 16: ...2 3 Oil system GX Pack Instruction book 14 2920 7105 31 ...
Page 18: ...2 4 Cooling system Pack units Instruction book 16 2920 7105 31 ...
Page 27: ...GX 7 EP IEC units with Y D start Instruction book 2920 7105 31 25 ...
Page 28: ...GX 7 EP for 208 230 460V 60 Hz DOL Instruction book 26 2920 7105 31 ...
Page 37: ...GX 7 EP Pack on 200l receiver 2 Cooling air inlet Instruction book 2920 7105 31 35 ...
Page 74: ......
Page 75: ......