Chapter One
1 - 14
Figure 1-10
Example layout for a typical Site Load Correction system.
The load bank starts up when the generator begins to operate and its control circuits
begin to monitor the output current. If this is below a certain set point then the load bank
will slowly apply additional load to bring the generator within the optimum range. If the
current increases in response to an increase in site load the load bank will remove load
accordingly. The load bank can do this very quickly in response to sudden changes of site
load such as a lift or pump motor starting up.
SLC is a specialist application for a load bank and it requires careful configuration. Please
contact Froment for more information and advice if you are thinking of configuring your
load bank for SLC.
Control Signal
Load Bank
Generator
Current
Transformer
Site Load
Utility Supply