4 - Covering  >> Using Arma-Chek D Covering

APPLICATION MANUAL   

 

D

© ARMACELL UK LTD.

Covering Of Insulated Objects >> Using Arma-Chek D Covering

END CAPS AND TERMINATION POINTS

Using self adhesive Arma-Chek D tape / bandage:

Self adhesive tape or bandage can be used to cover the 
open cell structure of the Armafl ex on oversize insulation 
covers. The “feathering” technique can be used (see pic-
ture). The length of the feathering should be two times 
insulation covers thickness. The edges of the “feather-
ing” should be reinforced using additional self adhesive 
tape or bandage material on both ends. (Note: bandage 
must be glued with the correct type of adhesive!)

   

  

   

  

Using covering:

Method 1:
1.  Measure the following diameters of the end cap: 
   a) small (insulated) pipe diameter and
   b) the large bore insulated body.
2.  Using Arma-Chek covering as a template, mark out 
   2 half-semi circles which have the following measure-
   ments:
   a) small bore insulated pipe outer diameter
   b) large bore insulated diameter of insulated body.
   Allowance should be made to both the inner side of 
   the  small  diameter  and  the  outer  side  of  the  large 
   diameter for feathering overlap length minimum equal 
   to the insulation thickness of the non covered area!
Method 2:
1. Measure the following diameters of the end cap:
   a) smaller  (insulated)  outer  diameter  of  insulated 
       body and
   b) the large outer diameter of insulated body.
2.  Using Arma-Chek covering as a template, mark out 2 
   circles  with  the  same  center  and  the  following 
   measurements
   a) outer diameter of small insulated body.
   b) large bore diameter of insulated body.

   Allowance should be made to both the inner side of 
   the  small  diameter  and  the  outer  side  of  the  large 
   diameter for feathering overlap of minimum equal to 
   insulation thickness of the non covered area.
3.  Cut out and modify the covering, fabrication using the 
   ”feathering“  technique.  When  installing  use  the 
   correct type of Armafl ex adhesive!
4.  For  the  quadrant  overlap  use  Arma-Chek  D  self-
   adhesive tape (in the correct size for the overlap) on 
   indoor  applications,  on  outdoor  applications  the 
   covering  material  (rolls),  which  can  be  cut  into  an 
   approximate trapezium shape for the best fi t.

   

  

SEAM AND JOINT DETAIL

Specifi cation Table for Arma-Chek D 

Product Type

Outdoor

applications

Indoor 

applications

Adhesive

+

+

Arma-Chek mastic

+

#

Arma-Chek D self-adhesive tape

+

Arma-Chek D strips

+

+  to be used
#  applicable  if  required,  in  locations  with  high  humidity  and 
  “wash-down” areas.

D (21)

Summary of Contents for Arma-Chek D

Page 1: ...application manual ARMA CHEK D application manual application manual ARMA CHEK D D...

Page 2: ...application manual ARMA CHEK D ARMACELL UK LTD D APPLICATION MANUAL D...

Page 3: ...ways use the correct speci ed Arma ex adhesives Do not assume they will always do the same job If in doubt consult the Armacell technical department local agent On external installations always ensure...

Page 4: ...ntire surface smoothing the covering round making sure there are no air pockets present Always check for alignment and avoid creases and crinkles during that time e If the surfaces are left to dry too...

Page 5: ...clean the seams and joints use the Arma ex cleaner Peel back release paper and cover the entire seam line with an additional 50 mm overlap where appli cable applying pressure during the installation C...

Page 6: ...General Working with Arma Chek D ARMACELL UK LTD D APPLICATION MANUAL 1 General Working with Arma Chek D 4 D...

Page 7: ...d x using the factory applied adhesive strip 5 Use correct Arma ex adhesive to secure the longi tudinal seam Apply on one side only Always remember to stagger longitudinal seams 6 Secure the butt end...

Page 8: ...seam of the throat using 20 mm wide Arma Chek S Butyl Tape Always ensure the tape is applied such that a watershed is achieved Note In some circumstances it may be preferable to fabricate segment ttin...

Page 9: ...ARMAFLEX TUBE Note Yellow lines indicate where cuts are to be made Always follow instructions related to the application of pre coated Arma Chek S tubes as stated in the above procedures relating to a...

Page 10: ...over the tting The oversize tting should extend by the wall thickness of the over sized fabrication minimum of 25 mm is required over the adjoining insulation On the butt end of the adjoining insulat...

Page 11: ...ness 1 mm 1 This table is valid for ambient conditions of 5 C For lower applica tion temperatures the rigidity and tension of the sheet material can increase thus lead ing to other conditions than men...

Page 12: ...e by drawing the half elevation on the edge of the Arma Chek sheet 4 Completed Arma Chek pipe reducer made of factory coated Arma Chek Dsheet material with a straight nish ECCENTRIC REDUCER FLAT BACK...

Page 13: ...meter of the connected pipes 2 x ins thickness Note 5 mm must be added to the jacket height deter mined 5 mm must be subtracted from all measur ments for openings 2 Cross section A A Determine the cir...

Page 14: ...borders directly on the ange with a 100 mm wide strip of Arma ex Determine the dimensions of the ductwork surface to be insulated On bends the inner throat and outer dimensions are determined using st...

Page 15: ...HANGING DUCTWORK Use the Arma x duct supports to optimize the preven tion of thermal bridging and simplify the hanging of duct work VESSELS 1 First insulate the vessel jacket with Arma Chek D pre coat...

Page 16: ...Insulating with Arma Chek D Using Pre Covered Sheets ARMACELL UK LTD D APPLICATION MANUAL 3 Insulating with Arma Chek D Using Pre Covered Sheets 14 D...

Page 17: ...are no gaps present in all the seams and joints Note Refer to the Arma ex Installation Manual at all times 2 For Arma Chek D covering adhesive is only required on the Arma ex and on the overlapping ar...

Page 18: ...ongitudinal seam of the covering with the correct Arma ex adhesive Continue to install the covering along the ductwork allowing for a 50 mm overlap on all butt joints DUCTWORK BENDS IRREGULAR SHAPES 1...

Page 19: ...seg ment of the assembled segment bend and determine the circumference 2 Transfer the circumference measurement U to the Arma Chek Dcovering material and draw in a line dividing it in half Now add a 5...

Page 20: ...pipe and transfer this to the covering material Halve the circumference 3 Transfer segment width for the throat seam to each end of the circumference drawn and the segment width for the back of the be...

Page 21: ...a pair of scissors OFFSET ANGLES 1 Determine the circumference U of the Arma ex in sulated offset angle the maximum a and minimum b height and the Arma ex insulated outer diameter of the pipe D to wh...

Page 22: ...material to the insulation material Secure the seams with Arma Chek D self adhesive tape on indoor applications with 100 mm wide strips of the covering material applied with all over adhesive coverag...

Page 23: ...eathering overlap length minimum equal to the insulation thickness of the non covered area Method 2 1 Measure the following diameters of the end cap a smaller insulated outer diameter of insulated bod...

Page 24: ...ARMACELL UK LTD D APPLICATION MANUAL 4 Covering Using Arma Chek D Covering Covering Of Insulated Objects Using Arma Chek D Covering 22 D...

Page 25: ...application manual ARMA CHEK D ARMACELL UK LTD APPLICATION MANUAL D D...

Page 26: ...ightweight and easy to apply insulation system resistant to mechanical impact D D Arma Chek R The insulation system with extra system security that minimises the risk of under insulation corrosion UIC...

Reviews: