Installation and Setup
47
Enova Digital Media Switchers - Hardware Reference Manual
Rack Installation and System Setup
Enova DGX 100 Series Switchers can be mounted in a standard EIA 19 in. (48.26 cm) rack.
Required Items
Enclosure
Enova DGX 6400 only – two rack mounting handles (provided)
Standard EIA 19 in. (48.26 cm) rack
Screwdriver
Screws that fit your rack for mounting the enclosure
Power cords (provided, if shipped within the US)
Surge-protector – highly recommended
Optional Items
PC or laptop computer with a null modem cable for communication with the enclosure via the RS-232 serial port
Recommendations
Write the serial numbers (normally located on rear of enclosure) in an easily accessible location before installing
the enclosure in a rack.
Use earth-grounded power cords and equipment with an Enova DGX Switcher.
Attach all power cords to a single surge protector and/or an AC line conditioner.
Apply power to the Enova DGX Switcher before applying power to its source and destination devices.
Installation Procedure
A flow chart showing the installation sequence is in FIG. 14. The procedure below the chart provides general steps with
references to detailed information found in later sections of the manual.
CAUTION:
To prevent overheating and airflow restriction, avoid placing high heat producing equipment directly above or
below the enclosure. The system requires a minimum of one empty rack unit above and below (three empty rack units are
recommended). Verify that the openings on the top and sides of the enclosure are not blocked and do not have
restricted air flow.
FIG. 14
Installation Procedure
Install in rack.
Attach first two video input and output cables.
If applicable, install appropriate TXs and RXs.
If applicable, wire first two connectors on audio board(s).
If applicable -
attach cable management bars for
DXLink Fiber Boards.
Establish connection from integrated Master to public
LAN via LAN 100/1000 port on CPU.
Apply power to enclosure(s) and then to system devices.
Launch System Configuration interface via browser
on PC connected to public LAN.
Execute a test switch.
Attach remaining video input and output cables.
If applicable, install remaining appropriate TXs and RXs.
If applicable, wire connectors on audio board(s).
If the system contains Audio Insert/Extract
Boards, they
must
be removed from the
system and the DIP switches on the
boards
must
be set to either insert or
extract audio according to system
requirements (see page 186).
If applicable -
remove AIE Audio Boards, set DIP
switches to insert or extract, and re-install in enclosure.
DXLink twisted pair cable runs for DXLink
Input and Output Boards are only to be
run within a
common building
.
("Common building" refers a building
where the walls of the structure(s) are
physically connected and the structure(s)
share a single ground reference.
IMPORTANT!
IMPORTANT!