COMMISSIONING
85
Step2
Step3
Check the running status of the system in “Step 3”.
If the operation is normal as described in “Step3”, please remember to deactivate
the “Charging/Discharging Setting” by clicking “OFF” and save the changes.
Select “
ON
” to Charge Batteries from Grid”
please set the “Charging period 1” for the time and the SOC
would be
100
under this operation.
The relative value should be like this:Load = PV
±
GRID
–
Battery
Battery should be in
charging
status.
PV arrow
should be as
the picture shows.
±
:
>>
absorbing from grid: +;
<<
feed-in to
grid:-
If not correct, please check the CT or meter installed direction
of both grid and PV side