COMMISSIONING
78
Hybrid Mode
Three mode options: DC/AC/
Hybrid
You can set the allowable feed-in ratio from 0%-100%.
Note:
When the safety standard is set as AS4777.2 (Australia and New
Zealand), the secondary sub-options can be selected according to
the region or local grid company.
On the grid side, if only a CT is installed, please select CT for grid
side.
If the grid meter is installed, please select Meter for grid side. If this
meter is a CT meter and the CT ratio is not 1, please select CT below
and input the Meter CT Ratio. If this meter is not a CT meter or the
Click “Submit” when the settings
are complete.
Storage PV capacity: PV capacity on the energy storage inverter side
Storage PV Capacity
5 kW
PV capacity on the PV-inverter (on-grid) side