COMMISSIONING
84
field, which has six fixed options (NSW, QLD, VIC, SA, TAS, WA). If SA is selected for
Region, two more fields are added which are Agent and NMI.
Fields that are not marked "optional" need to be filled in.
Click "Next" and go to Section 10.3 if the WiFi has not been configured.
9.5.
Check the Running State On-line
If you have completed commissioning as described in section 10.3.2, please ignore this
section.
You can also commission the system after WiFi configuration.
Please make sure the PV switch and battery breakers and all the breakers connecting
to the product are ON.
9.5.1.
Check the Charging Function of the Product
To make sure the system is installed and operating correctly, please set the
system to “Charging/Discharging Setting” by following the instructions below.
Step1
First click “
Function
” on the right-side bottom corner of the Home
page.
Then click “
Charging and discharging setting
”