Product Introduction and Application Scenarios
23
Step4:
Set on-grid capacity, storage ca-
pacity and number of PV strings (MPPT
number).
Step5:
Click the Battery Function and
check battery type SMILE5-BAT.
Step6:
Check SOC Calibration function
set No.
Step7:
Check the Battery Ready
function set No. If you only use the
inverter without battery, please set it
Yes.
Step8:
Click the Grid Function to set up
relevant parameters about the grid
Step9:
Set the Max. Feed in rate
value.
Step10:
Click Function-System Mode
to set system mode: DC, AC, Hybrid.
Step11:
Click Safety in the setting
menu. Set safety standard.
AS4777 for Australia, ARN4105 for
Germany, CEI0_21 for Italy, G83_2 for
Great Britain, NRS097_2_1 for South
Africa, RD1699 for Spain, VDE0216
for 60Hz countries.