4.7. SETTING THE MACHINE
INTO THE GROUND
Dig out a ditch in the floor in which to place the
template
(C)
and cast cement to fasten it into
place.
Template
(C)
is supplied on request (Optional).
|
Important
The depth
(X)
must be equal to the height of
the machine’s base plate.
4.8. RECOMMENDATIONS FOR CONNECTIONS
|
Important
Connections should be performed following the manufacturer’s indications in the enclosed diagrams.
Personnel authorised to perform this operation must possess technical skills, abilities and have acquired
certified experience in the specific field and must perform connections professionally, taking into account all
the regulative and legislative requirements. When connections are completed, make sure these requisites
were observed by performing a general inspection before making the unit operative.
4.9. PNEUMATIC
CONNECTIONS
Proceed as indicated.
1.
Insert a flexible tube on the end of the
rubber fitting and fasten it with a
metallic screw clamp
(A)
.
2.
Check that the valve
(B)
is in the "OPEN"
position.
3.
Turn on the power supply line.
4.
Check that the manometer reads a
pressure of at least
6 bar
and turn knob
(C)
to compensate any pressure
differences.
Repeat this operation with the machine
running.