![ADC Soneplex Soneplex Fiber Hub Cabinet SPX-CABFIN04 User Manual Download Page 34](http://html1.mh-extra.com/html/adc/soneplex-soneplex-fiber-hub-cabinet-spx-cabfin04/soneplex-soneplex-fiber-hub-cabinet-spx-cabfin04_user-manual_2848187034.webp)
Installation
LTPS-UM-8007-01, Issue 1
22
November 9, 2001
SPX-CABFIN01, SPX-CABFIN04
4
Remove the outer sheath to allow approximately 60 in. (1524 mm) of fiber to extend beyond the entrance to
the termination shelf.
5
Secure the outside plant cable(s) to the frame, using the cable clamp bracket provided with the 12A1 cable
clamps as shown in
. Mount the 12A1 clamp on the left vertical support, about 3 inches (76 mm)
below the bottom of the termination shelf.
6
Bond the metallic cable members to the frame, using a 6 AWG ground strap.
7
Following local practices, route the fiber cables into the shelves for buffering, connectorization, and
termination to build-out blocks as indicated on the engineering drawings.
8
Splice, following approved local practices.
Figure 16.
Fiber Cable Secured with 12A1 Clamps
Use a nonconducting fishtape to aid in running the fiber cables.
Washer
V-groove
insert
Ground
lug and
strap
Fiber
cable
Cable
clamp
Cable
clamp
V-groove
insert
Bracket
Nut
Nut