Prior to Installing the SPX-CABFIN
LTPS-UM-8007-01, Issue 1
10
November 9, 2001
SPX-CABFIN01, SPX-CABFIN04
1
Before pouring concrete, be sure that all four 1/2-13 anchor bolts are threaded all the way down in the
template anchor nuts.
2
Ensure that the wire mesh is set approximately 2 inches (51 mm) off the bottom of the form.
3
Pour the concrete. Puddle the concrete along all edges of the form.
4
Finish the concrete so that it is flush with, to 1/4 inch (6 mm) below, the top of the template mounting plates.
The pad should be level to within 1/2 inch (13 mm) over the entire length and width.
The pad must cure for a minimum of seven days before supporting any significant load, or before the cabinet
is installed. After the second day, the forms may be removed.
To keep concrete from entering during the pour, cover the duct openings.