Installation –
Installing the POLEMH6 on the EMH9996 foundation |
17
2
Lift the unlocked housing cover upwards, pull it off
the housing and set it aside.
y
Using a vacuum lifting tool or similar tool will
make it easier to lift off the housing cover.
1
2
3
Place the POLEMH6 on the foundation and run the
power and data cables through the base.
y
This step must be performed by two people.
NOTE
Cable lengths for connection
Please note the following recommendations when connecting the power and data cables:
Power line:
To connect to the terminal block on the lowest standard rail of the small distribution board, a
cable length of approx. 0.8 m from the foundation is recommended.
Data cables:
To connect to the bus interfaces of the eMH3 Wallbox, a cable length of approx. 2 m from the
foundation is recommended
4
Align the POLEMH6 over the holes on the foun-
dation and use the torque spanner to screw the
M10×35 hexagon socket screws over washers into
the threaded anchors of the foundation.
y
The allocation scheme for the thread anchor is