Operation Manual / TPL65VA10 / VA30
Maintenance
5
Cleaning the compressor during
operation
5.3
Page 63
© Copyright 2016 ABB. All rights reserved.
N
ov
em
ber
2016
H
ZT
L2487_
EN
R
ev
is
ion
C
Screw in the sealing plug (X).
Push the valve activator (Y) against the spring and hold it for 10 to
15 seconds until the entire volume of water has been injected.
After cleaning, wait at least 5 minutes to allow the turbocharger to dry.
NOTICE
If the cleaning operation is not satisfactory, it may be repeated up to
two times.
If the cleaning results are still not satisfactory after three attempts and
the engine values are also unsatisfactory, we recommend that you have
the turbocharger inspected and cleaned by an official ABB Turbocharg-
ing Service Station.
Cleaning parameters per turbocharger compressor
Product
Engine load
Contents of water vessel
[dm
3
]
TPL65
50 … 85%
0.4